A construction method and technology of sewage pipelines, which are applied in sewer systems, waterway systems, water conservancy projects, etc., can solve problems affecting the quality of life of residents and urban ecological appearance, lagging drainage facilities, and restricting rural development, etc., to shorten the construction period, The effect of reducing disturbance and improving engineering efficiency
Active Publication Date: 2019-10-08
CCCC SHANGHAI DREDGING
View PDF6 Cites 17 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
At present, most rural villages and towns do not have sewage pipes, and the drainage facilities are seriously lagging behind. Most of the sewage is discharged into farmland and streams nearby through ditches, causing certain pollution to the water bodies in the urban area, seriously affecting the quality of life of residents and the ecological appearance of the city, and restricting rural areas. develop
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0055] The present invention will be further described below in conjunction with accompanying drawing.
[0056] see Figure 1 to Figure 3 , the construction method of a kind of sewage pipeline of the present invention comprises the following processes: GPS positioning and lofting, road surface cutting and breaking, pipeline trench support and excavation, pipeline foundation construction, inspection well installation, pipeline installation, pipeline trench backfilling and road surface recover;
[0057] When carrying out the GPS positioning and stakeout process, according to the pipeline coordinate data provided by the design, carry out the stakeout of the sewage pipeline axis in the construction section, use GPS combined with the total station for detailed measurement and stakeout work, and determine the specific location of the construction according to the released well position;
[0058] When carrying out the pavement cutting and demolition process, follow the steps below: ...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
PUM
Login to view more
Abstract
The invention discloses a construction method of a sewage pipeline. The construction method comprises the following processes of GPS positioning and lofting, pavement cutting and breaking, pipeline groove supporting and excavation, pipeline foundation construction, inspection well mounting, pipeline mounting, pipeline groove backfilling, and pavement recovery. The pavement cutting and breaking process comprises the following steps of pipeline axis measuring and lofting, pavement cutting edge line marking, pavement cutting, and pavement breaking. When the pipeline groove supporting and excavation process is carried out, steel plate pile supporting is adopted when the depth is larger than 3.5 m. The pipeline foundation construction process comprises the following steps of foundation levelingand compacting, cushion layer paving, manual primary leveling, cushion layer compacting, and compactness detecting. The inspection well mounting process comprises the following steps of well bottom elevation rechecking, well bottom foundation checking, well chamber hoisting and splicing, and inspection well and pipeline connecting. The pipeline mounting process comprises the following steps of pipeline hoisting and manual mounting, pipeline axis positioning, pipeline joint cleaning, cutting, elevation and positioning retesting, and pipeline hot-melt welding or socket welding. According to theconstruction method, the construction period is greatly shortened, and the engineering efficiency is improved.
Description
technical field [0001] The invention relates to a construction method of a sewage pipeline. Background technique [0002] In order to make the rural living environment more and more beautiful, our country is comprehensively promoting the pace of rural domestic sewage treatment projects. At present, most rural villages and towns do not have sewage pipes, and the drainage facilities are seriously lagging behind. Most of the sewage is discharged into farmland and streams nearby through ditches, causing certain pollution to the water bodies in the urban area, seriously affecting the quality of life of residents and the ecological appearance of the city, and restricting rural areas. develop. [0003] Rural domestic sewage treatment mainly includes sewage collection projects, sewage treatment projects, and sewage upgrading projects. The sewage collection project mainly includes the laying of main and branch pipelines, inspection wells, and household pipes in each administrative ...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.