Construction process of cable crane hoisting system

A cable crane and construction technology technology, which is applied in cable cranes, cranes, transportation and packaging, etc., can solve the difficulty of horizontal and vertical transportation of components to the construction work surface, the mountain bridge has no rear balance section assembly site, and enlarge the pier. Beam joints and other problems, to achieve the effect of simple construction process, reducing span, and speeding up the construction progress

Pending Publication Date: 2020-08-25
CCCC SHEC FOURTH ENG +1
View PDF0 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Factors such as variable cross-section steel truss girders, long approach bridges, and their location on curves determine that traditional construction methods such as jacking are not suitable for the installation of main girders. Even if jacking methods can be used, bridges in mountainous areas do not have rear balance sections assembled At the same time, it i

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction process of cable crane hoisting system
  • Construction process of cable crane hoisting system
  • Construction process of cable crane hoisting system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0066] A construction process of a cable crane hoisting system according to the present invention, which includes a main anchor 01, a main load-bearing cable 02, a wind cable, a lifting trolley, a cable saddle, and a left-bank tower 05 and a right-bank tower 07. The steps are as follows:

[0067] (1) On the transition pier 010 on both sides of the bridge, construct the foundation embedded parts of the tower 05 on the left bank and the tower 07 on the right bank, and then assemble the tower 05 on the left bank and the tower 07 on the right bank, and install wind turbines on the corresponding towers. cable;

[0068] (2) Install the cable saddle on the top of the tower 05 on the left bank and the tower 07 on the right bank, and simultaneously carry out the construction of the main anchor 01 on both banks;

[0069] (3) Install the main bearing cable 02 and at the same time install the traction and lifting hoist;

[0070] (4) Carry out the installation of hoisting trolley, tractio...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a construction process of a cable crane hoisting system, and belongs to the field of bridges. The construction process comprises the following steps of step (1), respectively carrying out the construction of foundation embedded parts of towers on both sides on transition piers on both sides of a bridge, and then assembling the towers on both sides and installing wind cableson the corresponding towers; step (2), installing cable saddles on the tops of the towers on both sides, and carrying out the construction of main anchors on both sides; step (3), installing a main bearing cable and installing a winch at the same time; step (4), carrying out the installation of a lifting trolley, a traction rope and a hoisting rope; and step (5), carrying out hoisting system inspection and trial hoisting. According to the scheme of the invention, the towers are erected on the tops of the bridge transition piers, the span of a cable system is reduced and the height of the towers is reduced; and the arrangement not only greatly saves the construction cost and speeds up the construction progress, but also ensures the construction safety of a cable crane used in a large-span,variable cross-section steel truss continuous rigid frame bridge, and the hoisting construction process is simple.

Description

technical field [0001] The invention relates to the technical field of bridge construction, and more specifically, relates to a construction technique of a cable crane hoisting system. Background technique [0002] Due to the large-span variable cross-section steel truss girder continuous rigid frame bridge has a large spanning capacity and a light superstructure, it is a reasonable bridge structure form for crossing deep trenches, canyons and rivers. However, due to terrain constraints, these bridges are often difficult to install with large cranes, and it is even more difficult for large transport vehicles to reach each construction work surface. [0003] The current traditional construction technology of continuous rigid frame bridges at home and abroad generally adopts the push (drag) method and the cantilever assembly method of the bridge deck crane; for long-span steel truss bridges, if the cantilever is too large It is necessary to set up temporary buttresses between...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): B66C21/00B66C21/10E01D21/00
CPCB66C21/00B66C21/10B66C2700/011E01D21/00
Inventor 江超蔡俊华魏玉吉林金舜兰升元钟厚成庄燕珍廖小平张正宾王福桂陈理辉王赟
Owner CCCC SHEC FOURTH ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products