Coal face ultra-deep hole blasting roof cutting pressure relief control method and blasting charge structure
A coal mining face, roof cutting and pressure relief technology, applied in blasting, ground mining, mining equipment, etc., can solve problems such as small space, coal wall side and end face roof fall, and difficult hole sealing
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0035] like figure 1 , figure 2 As shown in the figure, a method for controlling ultra-deep hole blasting and pressure relief in a coal mining face includes the following steps:
[0036] (1) Based on the N structure of the overlying strata of the coal mining face F and the physical and mechanical parameters of the rock, the key stratum calculation method is used to calculate the key stratum N of the overlying strata of the No. , rock layer C, rock layer D and rock layer E, determine the key layer position of ultra-deep hole blasting topping as rock layer D, which provides a basis for the blasting top-cutting depth H and the design of the charging position of blast hole 5. The charging position includes blast hole 5 hard rock formations;
[0037] (2) Based on the production technical conditions of the coal mining face F, in the S1 and S2 parallel troughs on both sides within the range of 10m-30m in front of the stop line G of the coal mining face F, the construction is conve...
Embodiment 2
[0053] like image 3As shown, an ultra-deep hole blasting charge structure in a coal mining face includes a charge assembly, a detonation assembly and a hole sealing assembly. The charge assembly includes an energy gathering tube 1, an explosive charge coil 6, a detonating cord 2, a positioning Cotton 7, conical guide cap 8 and connecting head 9, wherein the energy-gathering tube 1 with directional fracture is used as a charge carrier, the explosive charge roll 6 is loaded in the energy-gathering tube 1, and the energy-gathering tube 1 A detonating cord 2 is laid along both sides of the explosive charge coil 6, and the two adjacent sections of the energy collecting tubes 1 are connected by the connecting head 9, and the detonating cord 2 passes through The whole process of laying is realized at the connection of two adjacent sections of the energy collecting pipes 1. The positioning cotton 7 is installed on the outer wall of the energy collecting pipes 1. 5 holes into the bot...