Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Large steel tube technology and equipment

A steel pipe and equipment technology, applied in metal processing equipment, welding equipment, welding equipment, etc., can solve the problems of difficult construction safety control, increased technical difficulty, and improved steel pipe construction safety and efficiency, and achieve the improvement of the automation level of manufacturing and installation machinery , Reduce the difficulty of hoisting and transportation, and reduce the effect of engineering costs

Inactive Publication Date: 2010-07-14
彭智祥
View PDF3 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Using traditional technology and equipment to weld bent pipes, vertical pipes and inclined pipes is still only assembled and welded in the factory, and transported to the installation site. This will form engineering constraints for the planning and construction of the production site, transportation roads, and hoisting equipment. For alpine valleys For steel pipe projects with large areas or large sizes, the technical difficulty will increase accordingly, and the project cost will inevitably increase, and its construction safety control is very difficult. On the one hand, there are risks in the transportation, turning and installation of large steel pipes. It is the systemic risk caused by the intersection between steel pipe construction and other simultaneous works. At the same time, when the hoisting equipment and site resources are limited, for example, during the construction of some dams, the construction of water diversion steel pipes will affect the construction period of the dam or even the entire project. will be direct
If the above-mentioned patented technology is adopted, although the transportation size of steel pipes can be reduced in some places, there are still great safety hazards in the transportation and installation stage of inclined pipes or vertical pipes because of size and weight problems, and it is difficult to increase the construction speed of steel pipes
[0004] It can be seen that there are the following deficiencies in the large-scale space steel pipe project: 1) The degree of mechanization and specialization in manufacturing and installation is insufficient; 2) The project cost increases due to the large transportation size; Efficiency needs to be improved

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Large steel tube technology and equipment
  • Large steel tube technology and equipment
  • Large steel tube technology and equipment

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0016] Embodiment 1: The manufacture and installation process and equipment of large-scale water delivery steel pipes in a hydropower station cavern, such as figure 2 As shown, the construction process is as follows: 1. Steel plate discharge and scribing; 2. Steel pipe sheet blanking; 3. Steel pipe sheet processing; 4. Steel pipe curled into tiles; 5. Tile inspection; 6. Steel pipe welding equipment (101) Installation and commissioning in the lower horizontal tunnel; 7. Tile transportation, including long-distance transportation to the construction tunnel, or secondary transportation to the construction tunnel of the lower horizontal tunnel after storage, and the tiles are transferred to the track trolley, using the inner track Transporting tiles; 8. The lower horizontal section of the steel pipe (102) is mechanically assembled on the welding equipment (101); 9. The longitudinal seam welding of the steel pipe section; Radius control; 11. Installation and welding of the stiffe...

Embodiment 2

[0018] Embodiment 2: The manufacture and installation process and equipment of large-scale water delivery steel pipes in a hydropower station cavern, such as figure 2As shown, the construction process is as follows: 1. Steel plate discharge and scribing; 2. Steel pipe sheet blanking; 3. Steel pipe sheet processing; 4. Steel pipe curled into tiles; 5. Tile inspection; 6. Steel pipe welding equipment (101) Install and debug in the lower horizontal hole, and install the winch lifting mechanism (110); 7. The tiles are transported and transferred to the track trolley, and the tiles are transported by the inner track of the pipe; 8. The first steel pipe in the lower bending section (112) 9. Steel pipe joint longitudinal seam welding; 10. Steel pipe joint adjustment: use the stroke adjustment on the rotary support (103) to control the radius; 11. Steel pipe joint longitudinal seam position Stiffening ring installation and welding; 12. The position adjustment of the first steel pipe ...

Embodiment 3

[0020] Embodiment 3: The manufacture and installation process and equipment of water delivery steel pipes in a large dam of a hydropower station, such as Figure 4 As shown, the construction process is as follows: 1. Steel plate discharge and scribing; 2. Steel pipe sheet blanking; 3. Steel pipe sheet processing; 4. Steel pipe curled into arc tiles; 5. Stiffening ring manufacturing, installation and welding; 6. The tiles are inspected and delivered; 7. The steel pipe assembly and welding equipment (101) is installed and debugged in the lower horizontal section (102); 8. The tiles are transported to the working range of the crane or cable lifting equipment and hoisted to the assembly and welding equipment; 9. The steel pipe of the lower horizontal section (102) is rounded on the assembly welding equipment (101); 10, steel pipe section longitudinal seam welding; 11, steel pipe section adjustment garden; 12, steel pipe section longitudinal seam stiffening ring installation and wel...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention aims to provide a new large steel tube manufacturing and installation technology and equipment. A unit structure taking tiles as the basis is adopted to transport large space steel tubes as well as install and weld on spot; installing and welding equipment adopts a steel tube positioning method and moves in the mode of flexible boosting or winching lifting of an axial cylinder; steel tube installation girth welding adopts rotation driving to drive an automatic welding device to finish the automatic welding of a space girth; mechanical operation can be realized when the steel tube is horizontal or is in an inclined, upper elbow or lower elbow state to form a set of large steel tube engineering center capable of multi-angle omnibearing moving. The invention replaces a traditional large space steel tube construction technology, is favorable for improving engineering safety, quality and efficiency, protects environment, lowers the integrated manufacturing cost of the steel tube and is especially suitable for large intake steel tube engineering in the cavity or dam of hydropower stations.

Description

technical field [0001] The invention belongs to the field of mechanical manufacturing, and relates to a manufacturing and installation process and equipment for large-scale steel pipes in hydropower stations, which are used for on-site assembly and welding of large-scale steel pipes. technical background [0002] In order to solve the technical problems of large-scale steel pipe manufacturing and installation under specific environmental conditions, the design of large-scale steel pipe mechanization process and steel pipe trolley came into being, which can complete the on-site manufacturing and installation of large or super large steel pipes in a limited construction space. Chinese patent application 200510020396.7 proposes a large-scale steel pipe automatic manufacturing process, and at the same time, Chinese patents CN2917917 (application number 200520035203.0) and CN1803567A (application number 200610020101.0) propose corresponding mechanisms to realize the mechanization ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): B23K31/02B23K37/00
Inventor 彭智祥彭智辉石昌玉
Owner 彭智祥
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products