Manufacturing method of pup joint
A manufacturing method and technology of short drill pipes, which are applied in the manufacture of short drill pipes for oil drilling and in the field of short drill pipes, can solve problems such as inability to carry out online, difficult production, and low product quality, so as to avoid quality problems, The effect of low processing cost and easy source
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0044] Embodiment one: a kind of manufacturing method of short drill rod, comprises following process steps:
[0045] (1) Heat treatment, straightening, and flaw detection of the pipe body: the heat treatment process is quenching + tempering process, the quenching medium is water, the quenching temperature is 880°C, the quenching holding time is 130 minutes; the tempering temperature is 620°C, and the tempering holding time 130 minutes; after the heat treatment is completed, use a six-roller straightening machine to straighten the full length of the pipe body; after straightening, use a flaw detector to perform full-length flaw detection on the pipe body;
[0046] (2) Sawing: cut the pipe body after heat treatment, straightening and flaw detection into 0.85m short material with a sawing machine;
[0047] (3) Preliminary machining: smooth the end face of the short material on the lathe, and then use the lathe to process the outer circle of the short material to Φ131.7mm, and th...
Embodiment 2
[0051] Embodiment two: a kind of manufacturing method of short drill rod, comprises following processing steps:
[0052] (1) Heat treatment, straightening, and flaw detection of the pipe body: the heat treatment process is quenching + tempering process, the quenching medium is water, the quenching temperature is 900°C, the quenching holding time is 110 minutes; the tempering temperature is 640°C, and the tempering holding time 110 minutes; after the heat treatment is completed, use a six-roller straightening machine to straighten the full length of the pipe body; after straightening, use a flaw detector to perform full-length flaw detection on the pipe body;
[0053] (2) Sawing: Cut the pipe body after heat treatment, straightening and flaw detection into 0.95m short material with a sawing machine;
[0054] (3) Preliminary machining: smooth the end face of the short material on the lathe, and then use the lathe to process the outer circle of the short material to Φ132.3mm, and...
Embodiment 3
[0058] Embodiment three: a kind of manufacturing method of short drill pipe, comprises following processing step:
[0059] (1) Heat treatment, straightening, and flaw detection of the pipe body: the heat treatment process is quenching + tempering process, the quenching medium is water, the quenching temperature is 890°C, the quenching holding time is 120 minutes; the tempering temperature is 630°C, and the tempering holding time 120 minutes; after the heat treatment is completed, use a six-roller straightening machine to straighten the full length of the pipe body; after straightening, use a flaw detector to perform full-length flaw detection on the pipe body;
[0060] (2) Sawing: cut the pipe body after heat treatment, straightening and flaw detection into 0.9-meter short material with a sawing machine;
[0061] (3) Preliminary machining: smooth the saw edge of the short material on the lathe, and then process the outer circle of the short material to Φ132mm with a lathe, and t...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com