Replacement filling treatment method for concealed argillaceous filled karst of tunnel bottom plate
A karst and floor technology, applied in tunnels, tunnel linings, earthwork drilling, etc., can solve the problems of large amount of replacement materials, large amount of excavation and backfilling workload, etc. The effect of saving labor and material costs
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] The present invention will be further described below in conjunction with the accompanying drawings.
[0030] Such as figure 1 Shown is a hidden mud filling karst replacement treatment method for the tunnel floor, which mainly includes the following steps:
[0031] Step 1. Hidden karst detection
[0032] On the tunnel floor, geological radar is used to scan the floor karst by arranging survey lines in a well-shaped pattern. According to the karst development boundaries detected by each survey line, the concealed karst development plane range is marked on the floor1.
[0033] Step 2: Drill holes, install orifice pipes and water inlet and outlet pipes
[0034] ① Design the drilling positions of the water inlet hole 2 and the water outlet hole 3 within the concealed karst development plane range 1, drill each hole to the top surface of the karst filling, and install the orifice pipe 4;
[0035] ② Carry out a flushing test on the karst muddy filling 7 taken out of the bo...