Multi-hydrogen acid construction process suitable for modification of sandstone reservoir
A technology for reservoir reconstruction and construction technology, which is applied in the directions of drilling composition, production fluid, wellbore/well components, etc., and can solve the problems of fast reaction speed, difficulty in effectively solving drilling and completion, short penetration distance, etc.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0030] Example 1: Acidification of injection wells in Hua XX-1 well
[0031] The acidizing layer in this well section is the 126-132# layer of Liu 1st Member, with a total thickness of 14.4m. The initial daily water injection volume is 6 ~ 15m 3 , The water injection pressure is 24MPa. According to a comprehensive analysis, with the prolongation of water injection time, the impurities contained in the layer continue to accumulate near the oil layer in the wellbore, blocking the formation pore and throat channels, resulting in a decrease in the water absorption capacity of the formation and an increase in the water injection pressure. In order to ensure the normal water injection of the well, it was decided to carry out acidizing injection.
[0032] The polyhydrogen acid system is used to carry out the polyhydric acid construction process for the well, and the acidizing construction steps are as follows:
[0033] S1, preparation 10m 3 The well pretreatment fluid, with 0.5m 3...
Embodiment 2
[0039] Example 2: Acidification of injection wells in Hua XX-2 well
[0040] The acidizing layer in this well section is the 197-212# layer of Liu 1st Member, with a total thickness of 10.6m. At the initial stage of betting, the daily water injection volume is 20m 3 , the injection pressure is 17MPa, which basically reaches the dispensing volume. With the prolongation of water injection time, the injection pressure gradually rises to 24MPa, and the daily water injection volume is only 16m 3 , unable to meet the required dispensing volume. According to a comprehensive analysis, the main reason for the difficulty of water injection in this well is that the physical properties of this layer are poor, and some pollution is caused during the operation and water injection process, which leads to an increase in injection pressure.
[0041] The well adopts the polyhydric acid construction process to deal with the blockage caused by the mud pollution near the well. The construction ...
Embodiment 3
[0048] Example 3: Acidification of injection wells in Hua XX-3 well
[0049] The acidizing layer in this well section is the 300-313# layer in the IV oil group of Liu 1 member, with a total thickness of 33.0m. The initial daily water injection volume is less than 5m 3 , The water injection pressure is 27.5MPa. The lithology of the target formation is pebble-bearing fine sandstone, loose, and the cuttings are loose sand. According to a comprehensive analysis, the main reason for the difficulty of water injection in this well is that the physical properties of the oil layer are poor, and impurities around the wellbore pollute the low-permeability layer, resulting in low water absorption capacity and high injection pressure.
[0050] The well adopts the polyhydric acid construction process to deal with the blockage caused by the mud pollution near the well. The construction steps are as follows:
[0051] S1, preparation 10m 3 The well pretreatment fluid, with 0.5m 3 / min dis...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com