Municipal roads and their construction methods
A technology of municipal roads and construction methods, which is applied to roads, roads, building components, etc., and can solve problems such as affecting traffic operation, large material voids, and easy cracks and potholes on the road surface
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0042] Embodiment 1, the construction method of municipal road, comprises the following steps:
[0043] Step S1: Positioning and setting out, determining the centerline of the road
[0044] Determine the centerline of the road according to the road conditions, and lay out the centerline control piles. The road centerline is composed of straight lines and curves. The straight line section control piles are arranged every 20 meters. Stakes need to be added at the pile number, and one pile is laid every 8 meters at the curve.
[0045] Step S2: Excavating roadbed trenches
[0046] Investigate the geological conditions of the project section, excavate the subgrade trenches according to the geological conditions, clean up the turf soil, tree roots, plants, etc. within the construction scope, excavate the road area and the soft soil layer under its influence, and clear the construction road section Excavate the 30cm thick humus soil layer in the road area, dispose of the waste bric...
Embodiment 2
[0066] Embodiment 2, the construction method of municipal road, its difference with embodiment 1 is:
[0067] Step S5: laying cement stabilization layer
[0068] The cement stabilization layer is made by uniformly mixing 45Kg of cement, 250Kg of lime, 350Kg of crushed stone, 30Kg of sand and 45Kg of water, and the particle size of the crushed stone is <20mm.
[0069] The paving mixture is used, the paving thickness is 19cm, and the rolling forming thickness is 15cm. A 15-ton vibratory roller is used to carry out static pressure four times at a speed of 1.8km / h, and then lightly shake twice with the vibratory roller. Finally, heavy Shock and crush twice.
[0070] Step S6: Spread emulsified asphalt
[0071] Remove dust, floating soil, loose layer and other sundries on the cement stable layer, repair and level off the local unevenness of the cement stable layer, and then spread modified asphalt 55Kg, water 38Kg, alkylphenol polymer on the upper surface of the cement stable laye...
Embodiment 3
[0077] Embodiment 3, the construction method of municipal road, its difference with embodiment 1 or 2 is:
[0078] Step S5: laying cement stabilization layer
[0079] The cement stabilization layer is made by uniformly mixing 50Kg of cement, 300Kg of lime, 400Kg of crushed stone, 40Kg of sand and 50Kg of water, and the particle size of the crushed stone is <20mm.
[0080] The paving mixture is used, the paving thickness is 19cm, and the rolling forming thickness is 15cm. A 15-ton vibratory roller is used to carry out static pressure four times at a speed of 1.8km / h, and then lightly shake twice with the vibratory roller. Finally, heavy Shock and crush twice.
[0081] Step S6: Spread emulsified asphalt
[0082] Remove dust, floating soil, loose layer and other sundries on the cement stable layer, repair and level off the local unevenness of the cement stable layer, and then spread modified asphalt 60Kg, water 40Kg, alkylphenol polymer on the surface of the cement stable layer ...
PUM
Property | Measurement | Unit |
---|---|---|
particle diameter | aaaaa | aaaaa |
thickness | aaaaa | aaaaa |
particle diameter | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com