Polytetrafluoroethylene sintering method capable of automatically controlling nitrogen inflation of nitrogen inflation sintering furnace
A technology of polytetrafluoroethylene and sintering method, which is applied in the field of polytetrafluoroethylene sintering that automatically controls the nitrogen inflow of nitrogen-filled sintering furnace, can solve the problems of waste, polytetrafluoroethylene is not wear-resistant, easy to creep, etc., and achieves Improve efficiency and quality, save nitrogen effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0014] Shut down to turn off the nitrogen system:
[0015] Using timing switch (time adjustable), the first nitrogen solenoid valve intake control device, the second nitrogen solenoid valve intake control device, and two solenoid valve intake control devices. After turning on the power, nitrogen gas is poured into the furnace body. At this time, the two channels of nitrogen are inflated, and the flow rate can be adjusted according to the demand (realized by the flow control valve and flow monitor). The heating time of the furnace is controlled by an intelligent multi-stage temperature control meter. The nitrogen setting time is generally 0~2 hours), after the temperature rises to the set temperature (the set temperature is generally 50~200 degrees Celsius, different temperatures are used according to different products), and then the nitrogen is turned off to ensure the environment in the furnace. Save nitrogen (at this time, the air in the furnace is basically expelled by the...
Embodiment 2
[0017] After shutting down, it is necessary to continue flushing nitrogen to prevent damage to products such as PTFE sealing rings (this type of furnace has good sealing effect, low nitrogen consumption, and better sintering effect)
[0018] Introduce PLC control mode (two-way nitrogen filling solenoid valve nitrogen filling time, and nitrogen closing time are freely controlled by PLC), PLC control device and the first nitrogen solenoid valve intake control device, the second nitrogen solenoid valve intake control With the cooperation of the device, two channels of nitrogen charging start at the same time after starting up, and the flow rate can be adjusted according to the demand (through the flow control valve and flow monitor). The furnace heating time is controlled by an intelligent multi-stage temperature control meter, and the two channels of nitrogen charging reach the predetermined time Then start to heat up (the setting time of nitrogen filling is generally 0~2 hours),...