New technology for recovering production and increasing production of shut down wells in pgz oilfield
A new technology and oilfield technology, which is applied in the direction of production fluid, earthwork drilling, wellbore/well components, etc., can solve the problem of increased dosage of water plugging and profile control agent, difficulty in water plugging and profile control, and premature dehydration of polymer gel And other issues
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2016-03-09
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the technique of increasing oil recovery in oil field exploitation, in particular adopting a profile control and plugging technique utilizing novel slow-swelling particles, microscopic flow direction changing agent and slow-swelling fixed changing agent. Background technique
[0002] In order to further improve the recovery rate of water flooding in the water cut period, since the 1950s, people have adopted profile control and water shutoff technologies such as adjusting the water absorption profile and redirecting fluid in deep oil layers. The research on the corresponding profile control and water shutoff reagents and their systems has also attracted the attention of many petroleum workers and researchers. In view of the actual situation that many oil wells in most oilfields are shut down due to excessive water flooding, and the remaining underground oil cannot be recovered, efforts to develop a plugging agent with excellent ...
Examples
Embodiment Construction
[0072] The technical solution of the present invention will be further described in detail through on-site examples below.
[0073] Well Wa 2658-4 began to produce water in October 2009, and the water content of the produced liquid reached 100%. The well was shut down in December 2011 to stop production. It is understood that during the period from October 2009 to December 2011, different units carried out two different oil increase measures on Well Wa 2658-4, but none of them achieved the effect of oil increase. During this period, the well produced fluid The moisture content is 100%. Shaanxi Kanglin Petroleum Technology Development Co., Ltd. started construction on Wa 2658-4 well on August 20, 2012.
[0074] 1. Reservoir data
[0075] The target layer is Chang 6, the perforated section is 1296-1300m, the effective thickness of the oil layer is 4m, and the fracturing sand is 22m 3 , The porosity is 11.07%, and the oil saturation is 38.13%.
[0076] 2. Construction purpose...