Contaminated foundation pit supporting and rapid excavation construction method
A construction method and foundation pit support technology, applied in the field of civil engineering, can solve the problems of long repair time, short repair period, complicated procedures, etc., and achieve the effects of safe and reliable construction process, low investment and operating costs, and simple construction steps.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0043] see figure 1 , a polluted foundation pit support and rapid excavation construction method, comprising
[0044] Step 1: Before the excavation of the polluted foundation pit, clean up the surrounding area of the polluted foundation pit, level the site, clean up the mud on the construction site, and then measure and stake out the construction site; divide the polluted foundation pit into the first work area, the second work area and the third work area;
[0045] Step 2: Set up a water retaining wall around the polluted foundation pit, which is formed by concrete pouring and arranged along the entire length of the perimeter of the polluted foundation pit; the water retaining wall formed by concrete pouring is 30cm high and 10cm thick; the polluted foundation pit is surrounded by drainage ditches Arrange a 1m by 1m by 1m water collection well every 50cm; and set a 0.3 by 0.3m intercepting ditch on the top of the polluted foundation pit at least 3m away from the excavation ...
Embodiment 2
[0053] see figure 2 , a polluted foundation pit support and rapid excavation construction method. Preferably, the soil nails are cement mortar soil nails, mainly using 16mm third-grade hot-rolled steel bars and M30 cement mortar for full-length soil nails. The construction method of inserting soil nails after grouting; prying off the pumice on the slope, cleaning the rock surface, and arranging the drilling positions; the mortar soil nails with a soil nail length less than 6m are drilled with a YT-28 hand-pneumatic drill , install soil nails after grouting; if the length of soil nails is greater than 6m, use YG80 guide rail rock drill to drill, install soil nails first and then grout; after drilling, wash the hole with high-pressure air and water, and drain the water blow out.
[0054] Among them, the permanent support soil nails that are grouted first are inserted into the soil nails immediately after the grout is filled in the borehole; the permanent support soil nails tha...
Embodiment 3
[0056] see image 3 , a polluted foundation pit support and rapid excavation construction method, preferably, in step 5, the first work area and the second work area, in the excavation process, firstly carry out the pollution boundary and the excavation boundary measurement and setting out, and then carry out multi-layer When excavating polluted soil, during the excavation process, excavation is carried out while supporting, and the excavation method adopts vertical layering, longitudinal segmentation, and branching along with excavation; after the upper layer of contaminated soil is excavated, the next layer of polluted soil The HDPE membrane is laid on the soil surface to separate, and the surrounding soil is cleaned during excavation, and the soil is tested and supported on the slope and pit wall;
[0057] The third industrial area is a heavily polluted area. First, the heavily polluted area will be closed with Larsen steel piles around it, and no excavation will be perform...