Long material processing device, hot dipping production line based on long material processing device and hot dipping method based on long material processing device
A technology for processing equipment and long products, applied in hot-dip plating process, metal material coating process, coating, etc., can solve the problems of large investment in equipment and materials, long process flow, smoke and dust pollution, etc., and achieve low capital investment in raw materials, Improve profit margins and reduce equipment investment
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0064] The product produced in this embodiment is a galvanized steel wire: the steel wire after the drawing is successively passed through the degreasing device, the washing device, the pickling tank device, the washing device, the plating aid device, etc., which are improved by the present invention, and the steel wire is degreased, washed, After pickling, water washing, and plating help, enter the hot-plating device with induction heating coil in the present invention, carry out fast induction heating (150~200 ℃) to steel wire, then pass through and load pure zinc (wt%Zn≧99%) The working pool (zinc liquid temperature 450-480 ℃), the pressure value at the upper end of the working pool is adjusted through the pressure control valve 3 during the working process, so that the zinc liquid level is higher than the two sides by a certain height through the hole, and then passes through the other side Lead out through the hole, use annular air knife (nitrogen at 200-300°C) for air kni...
Embodiment 2
[0066] The product produced in this embodiment is a hot-dip Galfan alloy steel wire, and the steel wire after the drawing is successively passed through the degreasing device, washing device, pickling tank device, water washing device, plating aid device, etc., which are improved and obtained by the present invention, to degrease the steel wire, After water washing, pickling, water washing, and plating help, enter the horizontal hot-plating device with induction heating coil described in the present invention again, carry out fast induction heating (150~200 ℃) to steel wire, pass through loading Galfan (Zn- 5wt%Al-Re) working pool (the temperature of the zinc liquid is 450-480°C, the pressure value at the upper end of the working pool is adjusted during the working process so that the Galfan alloy liquid level is higher than the two sides through the hole to a certain height), and then through another One side is led out through the hole, and an annular air knife (nitrogen at 2...
Embodiment 3
[0068]The product that the embodiment of the present invention produces is Φ 10 galvanized round steel (galvanized disc circle), adopts steel brush machine to carry out steel brush derusting by the wire rod that rolling obtains, removes the ups and downs of reinforcing bar surface through air knife purging then, and then The steel bar after derusting is introduced through the centering wheel, passes through the hot-plating device of the present invention, starts the induction heating coil to carry out high-frequency induction heating (600~800 ℃) to the steel bar under nitrogen protection, then passes through the working pool (wt%) Zn≧99%, pressure control and adjustment are the same as in Example 1), after being purged by an air knife, enter the water cooling device and passivation device for water cooling and passivation, and finally cut, pack, and store, and the horizontal hot-dip galvanized round steel production.