The invention provides a
subway station main body foundation pit structure in a complex environment and a construction method, and belongs to the technical field of
subway station main body foundation pit structures. The
subway station main body foundation pit structure structurally comprises a main body foundation pit formed in the complex environment of a three-face-ring building and a one-face-ring hillside, and a foundation pit structure is arranged in the main body foundation pit; the foundation pit structure comprises a pit edge base platform structure poured on the
peripheral edge of the pit bottom of a foundation pit body, a plurality of water collecting pits are formed in the four corners of the inner side of the pit edge base platform structure, a pit-in-pit base platform structure is poured in the middle of the pit bottom of the foundation pit body, and a plurality of foundation pit side wall structures are poured on the top face of the pit edge base platform structure in the direction corresponding to a three-face ring building. And a
water diversion filling layer structure is backfilled in the water accumulation prevention inclined pit in a layered non-tamping manner, so that the transverse
extrusion stress on an outer drainage wall structure is reduced, and the problems that in the prior art, the side wall of the foundation pit structure is transversely extruded by soil-
water pressure, and the side wall of the foundation pit structure is prone to
water seepage and
cracking are effectively solved.