Double-fluid grouting construction method for tunnel construction
A technology of tunnel construction and construction method, which is applied in the direction of tunnel, tunnel lining, earthwork drilling and mining, etc. It can solve the problems of double liquid slurry waste, long time of double liquid slurry consolidation, and failure to achieve the expected effect, so as to shorten the setting time, Effects of preventing clogging and reducing waste
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0028] Embodiment 1: a kind of double liquid grouting construction method for tunnel construction, comprises the following steps:
[0029] (1) Prepare and check equipment: move the equipment according to the ground conditions to be constructed, and check whether the equipment is operating normally;
[0030] (2) Drilling holes on the surface: use a water drilling machine to drill holes and make the grouting holes arranged in a plum blossom shape. When drilling the outermost grouting holes, the drilling angle should be 9-11°, and Drainage ditches shall be dug; the diameter of the grouting holes shall be 0.42m, the distance between two adjacent grouting holes shall be 0.35m, and the maximum deviation of hole positions shall be 0.05m; the drilling depth shall reach the designed grouting consolidation depth, and the The hole verticality error is less than 0.45%; when the predetermined depth is reached, flush the grouting hole with the maximum pressure and seal the nozzle of the gro...