A launch vehicle digital power supply and distribution control system and its test method

A technology for a launch vehicle and a control system, applied in the aerospace field, can solve the problems of large size of electromagnetic relays, large influence of switching transient effect test results, and occupation of space on the arrow, so as to save space and load on the arrow, and accurately respond to Emergency situations, the effect of reducing electromagnetic interference

Active Publication Date: 2022-05-20
北京中科宇航技术有限公司
View PDF4 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] Most of the traditional power distribution still adopts the control method of electromagnetic relay, which has the following defects: First, in order to ensure reliable power distribution and testing needs, it is necessary to adopt a redundant design in which multiple electromagnetic relays are connected in parallel through welding wires, and then through welding wires Connect the relay to the external connector, and use cables to build a large number of logic control circuits
Although this method is simple, it is heavy
Second: The electromagnetic relay is large in size, which is not suitable for soldering on the circuit board, and is not conducive to the integrated design of the equipment. Therefore, the traditional relay and distributor are often set up as a separate device, occupying the space on the arrow.
Third: The electromagnetic relay has a certain mechanical structure, and sometimes there will be abnormal contact of the electromagnetic relay due to environmental problems such as vibration and shock
Fourth: The electromagnetic relay is to adjust the on-off of the circuit by generating a magnetic attraction armature through the electrification of the coil. Because the coil has a certain inductance, electromagnetic interference signals are easily generated during the on-off process of the circuit. This is why it is difficult for electromagnetic distributors to pass the national military standard. The reason for the electromagnetic compatibility test, there are certain hidden dangers
Fifth: The driving mode of the electromagnetic relay leads to a longer response time for its shutdown, and the switching transient effect has a greater impact on the test results

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A launch vehicle digital power supply and distribution control system and its test method
  • A launch vehicle digital power supply and distribution control system and its test method
  • A launch vehicle digital power supply and distribution control system and its test method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0035] The application provides a digital power supply and distribution control system for a launch vehicle, including a power distribution control system for intelligent equipment and a power distribution control system for pyrotechnics. The length of the launch vehicle is relatively long, so the two ends of the rocket are respectively equipped with an intelligent equipment power distribution control system and an explosive power distribution control system. Such as figure 1 , 2 As shown, the intelligent device power distribution control system and the pyrotechnic product power distribution control system are respectively equipped with an instrument battery 11 and a pyrotechnic battery 21, so as to reduce the power consumption of the intelligent device power distribution control system and the pyrotechnic product power distribution control system powered by the same battery. Voltage loss due to long cables.

[0036] Both the intelligent equipment power distribution control ...

Embodiment 2

[0047] The present application also provides a test method for the digitalized power supply and distribution control system of the launch vehicle matched with the digitalized power supply and distribution control system of the launch vehicle in Embodiment 1.

[0048] The ground measurement and control system sends commands to close or disconnect each switch to the intelligent equipment power distribution control system and the pyrotechnic power distribution control system through Ethernet;

[0049] Each switch combination in the digital power supply and distribution control system of the launch vehicle executes the command after receiving the command;

[0050] Such as image 3 , 4 As shown, the data collection points 13, 14, 15, 23, and 24 are connected to the ground measurement and control communication, and the collection points 13, 14, 15, 23, and 24 are used to transmit the collected data to the ground measurement and control via Ethernet. Launch control, the data is dis...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses a digital power supply and distribution control system for a carrier rocket and a testing method thereof. The digital power supply and distribution control system for a carrier rocket includes a plurality of switches; the plurality of switches receive digital commands sent by the ground measurement, launch and control through the Ethernet to perform closing. Or disconnect action; the digital power supply and distribution control system of the launch vehicle sends the collected test data to the ground test launch control for analysis through Ethernet. This application transmits digital instructions and test data through Ethernet, which solves the problem that the cables used for ground test, launch and control become redundant loads on the arrow because they are no longer used after the rocket takes off.

Description

technical field [0001] The invention relates to the field of aerospace, in particular to a digital power supply and distribution control system for a launch vehicle and a testing method thereof. Background technique [0002] Compared with digital circuits and bus communication, the power supply and distribution system of my country's launch vehicles develops relatively slowly. The traditional power distribution control system and testing require many cables. Due to the needs of ground testing and logic control, many cables are directly led to the ground test and control system, and the ground test and control system performs multi-channel power distribution control, which greatly increases the number of arrows. The weight of the upper cable network, and many of these cables will not be used after take-off, these cables become unnecessary loads, affecting the rocket's carrying capacity. [0003] There are often multiple power supply and distribution systems on the launch veh...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): H02J7/00H02J13/00G05B23/02
CPCH02J7/007H02J13/00028G05B23/0213G05B2219/24065Y04S10/30Y02E60/00
Inventor 于继超朱永泉杨毅强辛哲奎郭文正
Owner 北京中科宇航技术有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products