Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Novel sloping field constructional engineering pile construction method

A technology for construction engineering and construction methods, which is applied in construction, infrastructure engineering, sheet pile walls, etc., and can solve the problem of the quality pass rate of punching cast-in-place piles. The quality of the pile connection and the complex construction process of the punched cast-in-place pile foundation can achieve the effect of avoiding the overturning of the mechanical platform, avoiding environmental pollution and site occupation, and shortening the time for connecting up and down piles.

Inactive Publication Date: 2021-01-12
CHINA CONSTR FOURTH ENG DIV
View PDF2 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] With the development of social economy, the requirements for production efficiency are getting higher and higher. In the construction industry, most of them are large-scale engineering construction. When it comes to large-scale construction of engineering piles, the mode of segmented construction is often adopted. In In the case of tight construction schedule and limited site conditions, the construction process of the foundation of punched cast-in-place piles (end-bearing piles) is complicated and the construction period is long
In the case of a tight construction schedule, it is difficult to carry out foundation excavation after all the perforated piles in the project have been constructed and tested; usually a part of the completed pile foundation is excavated in advance during the construction of perforated piles, but in During this process, the excavation of the deep foundation pit and its technical requirements will cause the pile top elevation of the punched pile to reach the bottom of the deep foundation pit, and then wait until the deep foundation pit is backfilled for secondary pile connection.
Because the construction of perforated piles is complicated and has a long construction period, and the backfilled soil layer is difficult to guarantee the forming quality of perforated piles, and the construction personnel need to carry out construction at a depth of 4-6 meters underground, and the operating space is narrow, It is difficult, and at the same time, it is difficult to guarantee the quality pass rate of punched cast-in-situ piles and the operation safety of construction personnel

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Novel sloping field constructional engineering pile construction method
  • Novel sloping field constructional engineering pile construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0044] Project Overview:

[0045] The construction area of ​​the project is about 220195.22㎡, of which the 6-storey building area of ​​B1 factory building is about 96354.5㎡; the 6-story building area of ​​B2 factory building is about 93917.5㎡; ㎡; the construction area of ​​the first floor of the S1 factory building is about 24462.04㎡; the construction area of ​​the first basement and the first floor of the equipment room is about 2207㎡; the construction area of ​​the first floor of the switch station is about 227.48㎡; ;

[0046] After adopting the new construction method of slope construction piles, the pile connection work can be carried out without earth backfilling, and the ground construction can be fully realized. The time for personnel to connect piles can be shortened by more than 75%. Compared with ordinary pipe piles, the pile connection time can be advanced The construction of the inserted pile project adopts a new construction method of slope construction engineeri...

Embodiment 2

[0052] Project Overview:

[0053] Building No. 5 of this project is 70.2m high, with 2 floors underground and 23 floors above ground, with a single-story building area of ​​563.64m 2 , with a total construction area of ​​13,000 m 2 , No. 6 residential building is 67.2m high, with 2 floors underground and 22 floors above ground, with a single floor area of ​​683.42m 2 , with a total construction area of ​​15,000 m 2 , Building No. 11 is a residential building with a height of 79.2m, 2 floors underground, 26 floors above ground, and a single-story building area of ​​789.2m 2 , with a total construction area of ​​20,500 m 2 , Building No. 12 is a residential building with a height of 9.10m, 0 floors underground, 2 floors above ground, and a single-story building area of ​​418.3m 2 , with a total construction area of ​​8,400 m 2 , Building No. 16 is 79.2m high, with 2 floors underground and 26 floors above ground, with a single-story building area of ​​794.04m 2 , with a tot...

Embodiment 3

[0060] Project Overview:

[0061] The total construction area of ​​this project is 34302.7㎡, with a tower building of 22 floors, a podium building of 3 floors, and two underground floors. The height of the tower is 98.5 meters. The structural system of the tower is a shear wall structure, and the basement is a frame structure.

[0062] After adopting the new construction method of slope construction piles, the pile connection work can be carried out without earth backfilling, and the ground construction can be fully realized. The time for personnel to connect piles can be shortened by more than 75%. Compared with ordinary pipe piles, the pile connection time can be advanced The construction of the inserted pile project adopts a new construction method of slope construction engineering piles, and the benefits produced are as follows:

[0063] It takes an average of 4 days to construct a pile with punching cast-in-place piles, while the average construction period of a pile is 1...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a novel sloping field constructional engineering pile construction method. The method comprises the steps that the specific position of an original punched cast-in-place pile is explored through ultrasonic waves, and a pile head of the original punched cast-in-place pile is excavated through a small excavator or manual earth excavation; after the pile head of the original punched cast-in-place pile is excavated, concrete of the pile head of the original punched cast-in-place pile is broken and chiseled through a cannon machine, the center of the pile head of the original punched cast-in-place pile is chiseled away, a groove is chiseled out, and the groove is 300 mm in length, 300 mm in width and 300 mm in depth; butt joint pile main reinforcements and original punched cast-in-place pile main reinforcements are in lap joint in a double-face welding manner, welding slag is removed in time after welding, then the butt joint pile main reinforcements are hooped, andthe diameter and the distance of stirrups of the butt joint pile main reinforcements are the same as those of the original punched cast-in-place pile main reinforcements; and by the adoption of the novel sloping field constructional engineering pile construction method, ground operation can be achieved in engineering pile splicing construction, pile splicing construction is convenient and rapid through ground operation, the quality level is improved, safety risks are reduced, meanwhile, the stress area of a pile foundation is increased, the stress performance of the pile foundation is improved, and the service life is prolonged.

Description

technical field [0001] The invention relates to the field of construction, in particular to a construction method for construction engineering piles on slopes. Background technique [0002] With the development of social economy, the requirements for production efficiency are getting higher and higher. In the construction industry, most of them are large-scale engineering construction. When it comes to large-scale construction of engineering piles, the mode of segmented construction is often adopted. In In the case of tight construction schedule and limited site conditions, the construction period of the punched cast-in-situ pile (end-bearing pile) foundation is complicated and the construction period is long. In the case of a tight construction schedule, it is difficult to carry out foundation excavation after all the perforated piles in the project have been constructed and tested; usually a part of the completed pile foundation is excavated in advance during the construct...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D9/00E02D37/00E02D5/64
CPCE02D5/64E02D9/00E02D37/00E02D2250/0007E02D2250/0023
Inventor 黎田尹土军柯灿荣欧阳锦乐吴骏骥方志红余程鹏
Owner CHINA CONSTR FOURTH ENG DIV
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products