Bidirectional pretensioning method prestressed concrete railway board and assembly machine sets method production process

A technology of track slabs and concrete, applied in the direction of tracks, roads, ballast layers, etc., can solve the problems of loss, inconvenient maintenance, high cost, etc., and achieve the effects of highlighting substantive features, improving work efficiency, and reducing production costs

Inactive Publication Date: 2006-11-22
欧阳炎
View PDF0 Cites 32 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] The track slab laid on the roadbed has been subjected to the pressure from the two steel rails for a long time, and the track slab is often cracked or broken due to external force deformation, thus causing unnecessary losses. At the same time, it is very difficult to maintain. Convenience; for this reason, in the manufacturing process of track slabs, steel bars or steel strands or steel rods or steel wires are often set in the track slabs and prestressed to reduce the deformation of the track slabs caused by external forces; The prestressing method of the track slab can be applied by the pre-tensioning method and the post-tensioning method. In practical applications, most of the existing track slabs are prestressed and post-tensioned concrete track slabs. The manufacturing process of prestressed and post-tensioned concrete track slabs is very complicated. The efficiency is low, and a large number of anchors are required to anchor the prestressed tendons, and the existing track slabs usually have steel cages to enhance the strength of the track slab, which greatly increases the cost of the track slab
[0004] In addition, the track circuit used in the railway signal system uses the rail as the transmission medium to transmit information about the idleness or occupancy of the section, as well as various information to control the operation of the train; the transmission performance of the track circuit is affected by line resistance, inductance, and the type of ballast bed. Influenced by many factors such as cleanliness and cleanliness, the limit length of the track circuit varies greatly under different line conditions; the slab track test section of the Qinshen Passenger Dedicated Line mainly draws on Japan’s experience and adopts two-way post-tensioned prestressed track slabs. Due to the post-tensioning process, in addition to the prestressed steel strands in the track slab, it is also necessary to configure ordinary steel cages to meet the strength of the track slab itself; the common steel cages for common post-tensioned prestressed track slabs , and the lower two layers of steel mesh. Each layer of steel mesh is composed of 20 F10 steel bars in the longitudinal direction and 30 F10 steel bars in the horizontal direction. The total mass of ordinary steel bars is 291kg. , forming many closed figures in geometric shape; when the track circuit is working, the alternating signal in the audio frequency range is transmitted in the rail, and when the current in the rail changes, an alternating magnetic field is generated around the rail, which is passed through electromagnetic induction in the rear A number of alternating induced currents are generated in the steel mesh in the tensioned track slab, and the alternating magnetic field generated by these induced currents will in turn prevent the change of the current in the rail; due to the generation of the induced current, the electric power transmitted by the track circuit is affected. The loss is caused, which leads to the shortening of the limit length of the track circuit; when the steel bar in the track slab is closer to the rail, the induced current formed in the steel mesh of the track slab is stronger, and the energy loss transmitted by the track circuit is more serious, and the limit length of the track circuit On the contrary, when the steel mesh in the track slab is farther away from the rail, the induced current formed in the steel mesh of the track slab is weaker, the energy loss of the track circuit transmission is less, and the limit length of the track circuit is longer; French experts require that steel bars can only be buried in the area below 40cm below the rail surface, in order to reduce the induced current generated in the track slab steel mesh to a small range, so that the electrical transmission function of the track circuit will not be affected too much, but There is no quantitative analysis of the data of 40cm; it is very difficult to realize that the track plate is more than 40cm away from the track surface, and the entire track structure will be completely changed
[0005] Based on the above reasons, researchers have been making unremitting efforts to study and constantly looking for new and practical methods to solve the problems of complex manufacturing process, high cost and unsatisfactory track circuit of concrete track slabs.
[0006] In order to solve the problem of the production process of concrete track slabs, on the basis of in-depth research and absorption, the researchers found that the post-tensioning method has many production processes, low production efficiency, and consumes a large amount of anchors, high cost and low product quality. It is not easy to guarantee and is not suitable for large-scale application; compared with the post-tensioning method, the production process of the pre-tensioning method is simple and the mechanical properties of the components are excellent, especially the cost of the components is greatly reduced; therefore, the production of prestressed two-way pre-tensioned concrete track slabs saves cost, simplify the process, and the mechanical properties of the components are excellent, and the loss of the track circuit is small. Because of this, in order to solve the problem of mass production of two-way pretensioned concrete track slabs, researchers continue to improve the existing production process, and actively test, gradually Enabling the production of two-way pretensioned concrete track slabs
[0007] At present, the process suitable for the mass production of track slabs is mainly the long-line pedestal production process, but it is not difficult to find in practice that the long-line pedestal production process cannot perform two-way discharge Zhang) can only produce prestressed post-tensioned concrete track slabs or prestressed unidirectional pre-tensioned concrete track slabs, but cannot produce prestressed two-way pre-tensioned concrete track slabs; as far as the developed countries of high-speed railways in the world are concerned, Japan The track slabs in China use two-way unbonded post-tensioned concrete track slabs. The Italian track slabs use longitudinal pre-tensioned and transverse post-tensioned concrete track slabs. my country’s Qinshen Passenger Dedicated Line uses two-way post-tensioned concrete track slabs based on Japan’s experience. Concrete track slabs by tensioning fixed pedestal method, so far, there is no precedent for mass production of two-way pre-tensioned concrete track slabs in developed countries of high-speed railways, and there is no record in relevant literature.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Bidirectional pretensioning method prestressed concrete railway board and assembly machine sets method production process
  • Bidirectional pretensioning method prestressed concrete railway board and assembly machine sets method production process
  • Bidirectional pretensioning method prestressed concrete railway board and assembly machine sets method production process

Examples

Experimental program
Comparison scheme
Effect test

specific Embodiment approach

[0033] Such as figure 1 As shown, a two-way pretensioned prestressed concrete track slab is in the shape of a cuboid. Various reserved structures are arranged on the track slab body 1, and two layers of steel wires are respectively arranged in the length direction and the width direction of the track slab body. , the steel wire 3 arranged along the length direction and the steel wire 4 arranged along the width direction are not in contact with each other, and the prestressed concrete track slab is pretensioned in both directions in the length direction and the width direction; the steel wire layer arranged along the length direction is about the track The center line 5 in the height direction of the plate body is symmetrically arranged, and the steel wire layers arranged along the width direction are symmetrically arranged about the center line in the height direction of the track plate body; the steel wires of each layer of steel wire layers are evenly distributed, and the ste...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a bidirectional pre-stress concrete track plate with significant electric property and lower producing cost, and relative production line. Wherein, the track plate is a cuboid, with several preset structures; there are at least two layers of steel wires inside the track plate along its length and width directions; the steel wires in said two directions do not contact each other; said pre-stress concrete track plate are tensioned along the length and width directions; the production method comprises: spraying demoulding agent, feeding material, tensioning, coating concrete, vibrating, maintaining, tensioning and demoulding. The invention can overcome the defects of present technique, with simple method, while it can be used to build high-speed railway.

Description

technical field [0001] The invention relates to the technical field of high-speed railway tracks, and more particularly, relates to a bidirectional pre-tensioned prestressed concrete track slab suitable for high-speed railway slag-free tracks and a production process thereof by assembly line method. Background technique [0002] With the continuous development of science and technology, the slag track is gradually eliminated due to its various disadvantages, and the slag-free track is gradually used in the construction of high-speed railways due to its high reliability, high ride comfort, high durability and almost no track maintenance. Adopted, but the key technology of the slag-free track lies in the track slab and its manufacturing process. [0003] The track slab laid on the roadbed has been subjected to the pressure from the two steel rails for a long time, and the track slab is often cracked or broken due to external force deformation, thus causing unnecessary losses. ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E01B3/34B28B15/00B28B23/04E01B1/00
Inventor 欧阳炎
Owner 欧阳炎
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products