Method for undisturbed switching between double power sources of hydraulic station of refuse incinerator
A waste incinerator and non-disturbance switching technology, which is applied in the direction of emergency power supply arrangements, electrical components, circuit devices, etc., can solve the problems of inability to charge, inability to output continuous control power, etc., to prolong the life of capacitors, reduce weight and volume, The effect of reducing the starting inrush current
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2014-08-27
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
Technical field
[0001] The invention belongs to the technical field of garbage power generation control, and relates to a method for undisturbed switching of dual power sources of a hydraulic station of a garbage incinerator. Background technique
[0002] As the contradiction between increasing garbage and limited processing capacity continues to intensify, power generation through garbage incineration is the main method to achieve garbage reduction, recycling and harmlessness. Among various waste incineration technologies, mechanical grate furnace incineration technology will be the mainstream incineration technology for domestic waste at present and in the future. The garbage enters the incinerator through the movement of the feeder, and then the full mixing and combustion of the garbage and the air are realized through the reciprocating motion of the grate. With the help of the boiler and the turbo generator, the conversion of chemical energy → thermal energy → electric energy...
Examples
Embodiment Construction
[0026] The technical scheme of the present invention will be further described in detail below in conjunction with the drawings and specific embodiments.
[0027] A non-disturbed switching method for dual power supplies of a hydraulic station of a garbage incinerator is characterized in that it comprises the following steps:
[0028] Step 1: Estimate the load, select the dual power switch
[0029] The main electrical equipment of the waste incineration power generation hydraulic station (oil station) includes two main oil pump motors, two cooling pumps and a heater, a DC power supply and a control system. The main oil pump motor and the cooling pump motor both work in one-use and one-backup mode. Therefore, only the power consumption of one main oil pump and one cooling pump is considered.
[0030] The total power of the power supply system is as follows:
[0031] P All = k p ( P OilPump + P CoolPump + P Heater + P DC + P ConSys...