Method for preparing marsh gas through straw, excrement and kitchen waste
A technology for kitchen waste and excrement, applied in biochemical equipment and methods, bioreactors/fermenters for specific purposes, bioreactors for gas production, etc., can solve the problem of incomplete biogas production, effect impact, process reaction time It is beneficial to large-scale popularization and application, stable operation, and shortening of anaerobic time.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] The straw and kitchen waste are crushed with a pulverizer, put into the pretreatment tank together with the feces, mixed for 7 hours, and then put into the premix tank for constant temperature heating and mixing to obtain a mixture;
[0030] Put the mixture into 2 anaerobic fermentation tanks in turn with a screw propeller and heat at constant temperature, stir and ferment for 36 hours to obtain biogas and fermentation residue respectively.
[0031] SO removal from biogas 2 , CO 2 Finally, put it in a buffer tank, dehydrate it, pressurize it to the gas storage tank, and get clean biogas; after the fermentation residue is separated, get biogas slurry and solid organic fertilizer; after the biogas slurry is left standing for 5 hours, discharge the supernatant, Get liquid organic fertilizer. Wherein, the above-mentioned constant temperature heating is heated and controlled by a solar device, and the temperature is 38-48°C.
Embodiment 2
[0033] Crush the straw and kitchen waste with a pulverizer, put them into the pretreatment tank together with the feces, and then add municipal sludge accounting for 10% of the weight of the whole straw, feces and kitchen waste to the pretreatment tank, mix for 6 hours, and then Put it into the pre-mixing tank and heat it at a constant temperature, mix it evenly, and get the mixture;
[0034] Put the mixture into two anaerobic fermentation tanks with a screw propeller and heat it at a constant temperature, stir and ferment for 48 hours to obtain biogas and fermentation residue respectively.
[0035] SO removal from biogas 2 , CO 2 Finally, put it in a buffer tank, dehydrate it, and pressurize it to the gas storage tank to obtain clean biogas; after the fermentation residue is separated, biogas slurry and solid organic fertilizer are obtained; after the biogas slurry is left to stand for 6 hours, the supernatant is discharged, Get liquid organic fertilizer. Wherein, the abov...
Embodiment 3
[0037] Grind the straw and kitchen waste with a pulverizer, put them into the pretreatment pool together with the feces, and then add municipal sludge accounting for 15% of the weight of the whole straw, feces and kitchen waste to the pretreatment pool, mix for 8 hours, and then Put it into the pre-mixing tank and heat it at a constant temperature, mix it evenly, and get the mixture;
[0038] Put the mixture into two anaerobic fermentation tanks with a screw propeller and heat it at a constant temperature, stir and ferment for 24 hours to obtain biogas and fermentation residue respectively.
[0039] SO removal from biogas 2 , CO 2 Finally, put it in a buffer tank, dehydrate it, pressurize it to the gas storage tank, and get clean biogas; after the fermentation residue is separated, get biogas slurry and solid organic fertilizer; after the biogas slurry is left standing for 3 hours, discharge the supernatant, Get liquid organic fertilizer. Wherein, the above-mentioned consta...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com