The invention provides a quick hot-line by-pass
jumper overlapping operation method for a 10kV insulated power distribution line. The operation method is cooperatively implemented by a work leader, an on-post ground potential operation electrician and two ground operation electricians. A ground potential operation method is adopted and mainly comprises the operation steps of applying for stopping using re-closing equipment, taking insulation isolation measures, making a preparation for overlapping, stripping off a
middle phase conductor insulating layer, overlapping a
middle phase joint, overlapping two side phase joints, removing insulation isolation measures, restoring the re-closing equipment of the line and the like. The quick hot-line by-pass
jumper overlapping operation method for the 10kV insulated power distribution line has the advantages that the operation method is convenient, quick, time-saving and labor-saving, the working efficiency can be greatly improved, the limitations and the defects of the traditional direction operation methods by using an
aerial lift device with an insulating arm and insulating sleeves are overcome, the reliability of power supply guarantee is improved and the range of hot-line operation items of a power distribution network is widened.