The present invention relates to an offshore wind farm wind
turbine installation
engineering ship and an operation method thereof, comprising a main
hull of a double-side structure, a main
deck welded on the top, a crawler crane installed on the main
deck, the crawler crane divides the main
deck into a component
storage area and an
impeller assembly area, a main crane is installed in the
impeller assembly area, the main crane is located on the right side of the main deck, and an elephant leg tooling is also installed on the side in front of the main crane; a
ballast tank balanced with the main crane is arranged in the main
hull located at the other side of the main deck; when in use, the crawler crane cooperates with the auxiliary crane to buckle the hub upside down onto the elephant leg tooling, and then the main crane cooperates with the crawler crane to sequentially hoist three blades onto the hub to assemble into an
impeller, and finally the main crane cooperates with the crawler crane to hoist the impeller as a whole to the impeller
assembly at sea to complete the installation. The
engineering ship of the present invention has a reasonable
layout, a large
carrying capacity, a large operating space, and can meet and be suitable for safe, efficient and free offshore operations.