The invention discloses a high-speed railway full-process digital cleaning construction method, and particularly relates to the technical field of high-speed railway digital construction, the construction method comprises the following steps: S1, determining and rechecking line
design data; s2, line measurement and
pile placement are conducted, operation is conducted in cooperation with cleaning work according to the
quality control standard, an auxiliary measurement
system is used for being combined with a
distance measurement module to measure the rail surface elevation of the line after cleaning, and therefore the elevation condition of a cleaning section is controlled in real time; s3, constructing a
daily operation process; s4, primary tamping operation is carried out; s5, carrying out coarse tamping operation; s6, fine smashing operation is carried out; s7, fine tamping operation is carried out again, after the second
track gauge fine adjustment is completed, tamping operation is carried out again through the fine tamping scheme manufactured through inertial navigation operation fine measurement data, tamping stabilizing operation is carried out, and meanwhile whether reinforcing tamping is carried out or not is determined according to the TQI, the fine measurement data and other conditions; and S8, carrying out quality re-inspection and analysis, carrying out appearance arrangement and acceptance, and then carrying out
project completion.