The invention belongs to the technical field of
tunnel construction methods, and particularly relates to a tunnel anchoring and grouting integrated construction method, which comprises the following steps: firstly, excavating a tunnel face, constructing sprayed concrete and local anchor rods of an arch ring part, then, carrying out secondary primary support, and starting to construct grouting anchor
pipe support and grouting at a position which lags behind the tunnel face by 50m; the construction method comprises the following steps of: firstly, pouring a bottom plate of the section, constructing a waterproof and drainage
system of the arch wall, and pouring a secondary lining of the arch wall and a vault at one time, optimizing complicated procedures, organically combining support anchor rod construction with a radial grouting process, and realizing systematic grouting on an excavated rock surface by utilizing an existing grouting anchor
pipe. The expansion shell type radial grouting anchor
pipe is adopted for radial grouting
water stop construction, the supporting function of the grouting anchor rod is achieved, meanwhile, grouting
water stop and surrounding rock reinforcement are carried out on the fractured rock
mass, and on the premise that the construction requirement is met, the construction progress is greatly shortened, and damage to tunnel surrounding rock is reduced.