The invention discloses a railway existing
double crossover integral
insertion and pavement construction method. The method comprises the following steps that 1, a pre-paving site is selected; 2, a
double crossover is paved in advance, and control piles on the two sides of the
double crossover are rechecked and accepted; 3, the double
crossover is reinforced; and 4, double
crossover sliding ways are arranged, the double
crossover is integrally inserted and laid in place, an existing line in the inserting range is detached according to the design position in the
skylight point, a
ballast bed iscleared, the double crossover is slowly and transversely moved forwards, and the force of each part is guaranteed to be uniform. Compared with railway existing double crossover disintegration
insertion and pavement, double crossover integral
insertion and pavement is adopted, so that the number of the skylights is saved, the influence on normal transportation of the railway is reduced, the construction period is short, the efficiency is high, the overall structural size of the double crossover after being inserted is good, the diseases are few, the later maintenance cost is greatly reduced, the railway transportation is safe and reliable, the economic benefit is obvious, and the method can be widely popularized and used.