The invention belongs to the technical field of road paving, and particularly discloses a construction method for large-thickness paving of a
cement-stabilized gravel base layer, which comprises the following steps: screening a gravel material, controlling the ratio of
cement to the gravel material during mixing, controlling the
water content to be 4.77%, adding water according to the environment temperature, controlling the
maximum dry density to be 2.365 g / m < 3 >, and constructing an earth shoulder during paving. Controlling the thickness and the speed of virtual paving by paving, rolling by using road rollers with different tonnages, finishing the surface until no wheel mark exists after initial pressing, re-pressing and final pressing, then performing depth detection, and finally performing film covering and watering maintenance; by strictly controlling the content of raw materials and
cement, the
water content, the
maximum dry density, the paving thickness and
grinding, shrinkage cracks caused by sudden change of water gradient are reduced, so that the problems that the water
evaporation speed of the raw materials of the cement-stabilized base layer in an
arid climate region is too high in the subsequent construction stage, the shrinkage cracks appear on the cement-stabilized base layer, and the construction quality is influenced are solved. Therefore, the strength is reduced.