The invention relates to the technical field of bridge construction, and particularly discloses a
cliff-near
deep water area
cantilever casting arch bridge skewback construction method which comprises the following steps: S1, building a
cofferdam: outwards extending at a designed skewback construction position to build the
cofferdam which is a steel-concrete structure with a front wall adopting a steel
cofferdam; step S2, arranging an inner support: synchronously performing inner support construction and
water pumping in the cofferdam in the built cofferdam, and just evacuating
river water in the cofferdam when the inner support construction is completed; s3, arch support pouring is conducted, specifically, after the inner supports are arranged, arch support pouring is completed before the target low
water level period; and S4, 1 # section arch section construction is conducted, specifically, the steel structure is dismantled in the target low
water level period, and 1 # section building is completed. The technical problems that in the prior art, the size of the skewback becomes large, in the construction environment of
deep water near the
cliff, the construction space is forced to become small near the
cliff, a cofferdam needs to be built firstly due to the
deep water, the construction space is further compressed, and construction is difficult to complete through a construction scheme in the prior art are solved.