The invention discloses an LNG (
Liquefied Natural Gas) ship bulwark section construction method which specifically comprises the following steps: S1, bulwark section
assembly division: dividing a bulwark section into a plurality of assemblies, and respectively constructing and folding; s2, assembling and building in a main
deck; s3, after the top outer plate small assemblage and the main
deck small assemblage are built, the main
deck small assemblage is assembled on the segmented plane jig frame with the side outer plate as the
base plane, and a main deck middle assemblage is formed; s4, outer inclined side plate middle assemblage building; s5, after the outer inclined side plate small assemblage and the bulwark deck small assemblage are built, the outer inclined side plate serves as a
base plane, the bulwark deck small assemblage is assembled on the segmented plane jig frame, and an outer inclined side plate middle assemblage is formed; s6, assembling and building in a bulwark deck; s7, inner inclined side plate middle assemblage building; and S8, the bulwark sections are assembled, specifically, the main deck middle assemblage, the bulwark deck middle assemblage and the outer inclined side plate middle assemblage are assembled with the inner inclined side plate as the
base plane, and the bulwark sections are formed. According to the invention,
assembly construction is adopted, so that the
workload of the segmented tire position is decomposed to each small
assembly stage and each middle assembly stage, and the complexity of segmented manufacturing is simplified.