Patents
Literature
Hiro is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Hiro

35results about How to "Reduce job cycle time" patented technology

Construction method for soft rock deformation tunnel lining support dismantling-replacing arch

The invention provides a construction method for a soft rock deformation tunnel lining support dismantling-replacing arch. One-time whole section integral dismantling and replacing of a lining support is achieved. The construction method has the advantages that before dismantling and replacing, a lining which loses bearing capacity is subjected to grouting reinforcement treatment first, then a temporary cover arch is additionally arranged outside for reinforcement, and afterwards, the lining support is dismantled step by step, so that potential safety hazards caused by dismantling or removing of a temporary platform frame are avoided, and some security risks are avoided effectively. According to the construction method, the construction difficult problem of soft rock large deformation occurs during construction of a tunnel in special and complex geology is solved. Through the created novel construction method, the construction difficult problem of second lining cracking deformation needing remediation due to weak surrounding rock large deformation is solved. Through the construction method, safe, fast and economic treatment and remediation of the lining support and arch replacing construction are achieved, and the tunnel structure stability and construction safety are ensured effectively.
Owner:CCCC SECOND HIGHWAY ENG CO LTD

Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method

ActiveCN102562075AMeet the requirements for enhanced controlsSpeed ​​up early closure timesUnderground chambersTunnel liningShortest distanceRock tunnel
The invention discloses a large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method, which comprises the steps as follows: (1) annularly excavating an upper step of an upper part arc pilot tunnel, transferring excavated earthwork of the upper step to a lower step; (2) excavating a left part of a middle step about 4.5-5 meters behind the upper step, and transferring excavated earthwork to the lower step; (3) excavating a right part of the middle step about 3-4 meters behind the left part of the middle step, and transferring excavated earthwork to the lower step;(4) excavating a left part of the lower step about 6-8 meters behind the left part of the middle step or about 3-4 meters behind the right part of the middle step, and conveying excavated earthwork of the left part of the lower step out of the tunnel; (5) excavating a right part of the lower step about 3-4 meters behind the left part of the lower step, and conveying excavated earthwork of the lower step out of the tunnel; and (6) excavating the rest part of the tunnel bottom about 20-25 meters behind the right part of the lower step, excavating continuously according to the steps in a circulating and interlacing manner, and finally realizing tunnel excavating construction. The method can be used for building a large cross-section tunnel in a safe, rapid and economic manner.
Owner:CCCC SECOND HIGHWAY ENG CO LTD +1

Double-pump hydraulic control loop of key drilling action of cutting drill rig

A double-pump hydraulic control loop of a key drilling action of a cutting drill rig comprises a double linkage load-sensitive variable pump set, a double oil intake linkage load-sensitive multi-way valve, a rotary motor, a propulsion motor, a drilling logic control block, a rotation guide handle, a propulsion guide handle, and a hydraulic oil tank. An oil inlet of the double linkage load-sensitive variable pump set is connected with the hydraulic oil tank. An oil outlet and a load-sensitive opening are connected with an oil inlet and a load-sensitive opening of the double oil intake linkage load-sensitive multi-way valve respectively. Each valve pressure difference compensator of the load-sensitive multi-way valve is provided with an external control opening. The external control openings are connected with the drilling logic control block. The rotation guide handle and the propulsion guide handle are connected with the drilling logic control block or a guide control opening of the load-sensitive multi-way valve. The double-pump hydraulic control loop has the advantages that power head rotation-proportion-controlled propulsion is achieved, independent load-sensitive control of rotation and propulsion is achieved, propulsion speed is increased, and the like.
Owner:SUNWARD INTELLIGENT EQUIP CO LTD

Rough-terrain wheeled crane

The utility model discloses a rough-terrain wheeled crane of which all actions are driven in a full-hydraulic manner, and the rough-terrain wheeled crane can realize stepless speed change and has stable speed according to different work conditions, has the advantages of small impact, simple chassis arrangement, light complete vehicle weight, and is portable, safe and reliable in operation. The rough-terrain wheeled crane is provided with an electrohydraulic control system, a driving device and a steering device which are used for realizing fast switch among a plurality of driving modes and steering modes, thereby achieving small turning radius, fully exerting the power performances of an engine, improving the fuel oil economy and saving energy resources. The rough-terrain wheeled crane has a special underframe of an integral box type closed structure and is separately and rigidly suspended, an arc-shaped crane arm and an X-shaped telescopic support leg ensure good cross-country performance, mechanical property and working condition adapting performance of the entire rough-terrain wheeled crane during running and operating. The rough-terrain wheeled crane is convenient to maintain, and especially suitable for small construction places such as airports, oil fields, ports, wharfs, storehouses and other building sites.
Owner:湖南中铁五新重工有限公司

Excavator bucket capable of preventing soil adhesion

The invention discloses an excavator bucket capable of preventing soil adhesion. The excavator bucket comprises an external bucket body, a internal bucket body, a baffle ring and a cam unit. The internal bucket body is hinged inside the external bucket body; the baffle ring is mounted at the flared end of the external bucket body and used for guiding materials into the internal bucket body; and the cam unit is mounted on the external bucket body to make the internal bucket body swing back and forth inside the external bucket body. The excavator bucket capable of preventing soil adhesion can unload the soil in the bucket effectively, and shorten the working time of an excavator, and the effective bucket capacity of the excavator bucket is improved.
Owner:山东鲁宇重工机械制造有限公司

A kind of ventilating system of underground tunnel

The invention relates to a ventilation system, in particular to an underground blind tunnel ventilation system. Local ventilating fans of the system are arranged in a crossdrift, one inlet-outlet of the local ventilating fans is formed in a working face range of a blind tunnel through a drainage air barrel, the other inlet-outlet is connected to a branch barrel with an opening facing the wind direction and a branch barrel with an opening opposite to the wind direction in the crossdrift through a tee joint respectively, an air channel switching valve plate for opening and closing the two branch barrels is installed at the position of the tee joint, a smoke dust sensor is arranged at the rear end of the drainage air barrel, a smoke dust sensor is also arranged at the front end close to the drainage air barrel, of the blind tunnel, and the smoke dust sensors are connected with a fan control module through data lines. The problem that traditional system smoke dust air flows are in relatively-balanced low-efficiency state is solved, smoke dust close to the head-on position performs outwards diffuses and moves to an effective suction distance or effective range of the air barrel so as to effectively improve the smoke dust explosion efficiency in blind tunnel tunneling operation work.
Owner:YILIANG CHIHONG MINING IND

A mining method for broken and inclined medium-thick ore bodies with surrounding rocks on the hanging wall

The invention discloses a mining method for a hanging wall surrounding rock broken inclined medium thick orebody. Stope division is carried out on the orebody along the orebody trend, broken ores aretransported in stages, subsections are divided within the stages, sublevel drift mining method is adopted in advance for stoping and filling of the orebody close to the hanging wall, the drift too plates of at one ends of all sublevel mining drifts close to a heading wall are interconnected to form a slope, thus making preparations for trench ore-drawing and enabling trench ore-drawing at all subsections, then a bottom-up stoping sequence is employed for stoping and filling of each subsection orebody, thereby effectively solving the problem of potential safety hazard when a carry scraper enters a stope for a long time. In addition, implementation of downward fan-shaped medium-deep holes improves the rock drilling efficiency and safety, all construction guarantees no destruction to the hanging wall broken surrounding rock, also a rock drilling gallery is employed as the air-return way, and the problem of difficult ventilation is effectively solved. The method provided by the invention generally shows significant security measures in ore drawing, rock drilling and ventilation of middle-low grade hanging wall surrounding rock broken inclined medium thick stable orebodies.
Owner:CENT SOUTH UNIV

Method for excavating subway station through middle steel pipe vertical columns

The invention relates to the technical field of construction engineering, and discloses a method for excavating a subway station through middle steel pipe vertical columns. The method comprises the steps that after an upper step 1 and an upper step 2 are excavated, upper core soil is removed, reinforced concrete is poured on a foundation, bolts are pre-buried, steel supports are erected, the steel supports are connected with the foundation, movable heads are arranged, a square timber is erected above the movable heads, the steel supports are connected through angle iron, and after deformation is stable, the temporary steel supports are removed. The influence of perturbation on surrounding rock during blasting excavation is reduced, stress of the surrounding rock is released advantageously, construction processes are more optimized, deformation of the surrounding rock is better controlled, the defects that by adopting a traditional method, in rock column removing, the high-altitude operation safety risk exists, the construction difficulty is large, and the technology is complex are overcome, meanwhile, an upper step excavating process operation platform is fully utilized, thus the construction difficulty is lowered, construction operation is facilitated, segmented timely support is achieved, the operation circulation time is shortened, the tunnel excavating speed is effectively increased while safety is ensured, and the construction processes are reduced.
Owner:CHINA CONSTR COMM ENG GRP UNITED +2

Double-pump hydraulic control loop of key drilling action of cutting drill rig

A double-pump hydraulic control loop of a key drilling action of a cutting drill rig comprises a double linkage load-sensitive variable pump set, a double oil intake linkage load-sensitive multi-way valve, a rotary motor, a propulsion motor, a drilling logic control block, a rotation guide handle, a propulsion guide handle, and a hydraulic oil tank. An oil inlet of the double linkage load-sensitive variable pump set is connected with the hydraulic oil tank. An oil outlet and a load-sensitive opening are connected with an oil inlet and a load-sensitive opening of the double oil intake linkage load-sensitive multi-way valve respectively. Each valve pressure difference compensator of the load-sensitive multi-way valve is provided with an external control opening. The external control openings are connected with the drilling logic control block. The rotation guide handle and the propulsion guide handle are connected with the drilling logic control block or a guide control opening of the load-sensitive multi-way valve. The double-pump hydraulic control loop has the advantages that power head rotation-proportion-controlled propulsion is achieved, independent load-sensitive control of rotation and propulsion is achieved, propulsion speed is increased, and the like.
Owner:SUNWARD INTELLIGENT EQUIP CO LTD

Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method

ActiveCN102562075BMeet the requirements for enhanced controlsSpeed ​​up early closure timesUnderground chambersTunnel liningShortest distanceRock tunnel
The invention discloses a large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method, which comprises the steps as follows: (1) annularly excavating an upper step of an upper part arc pilot tunnel, transferring excavated earthwork of the upper step to a lower step; (2) excavating a left part of a middle step about 4.5-5 meters behind the upper step, and transferring excavated earthwork to the lower step; (3) excavating a right part of the middle step about 3-4 meters behind the left part of the middle step, and transferring excavated earthwork to the lower step;(4) excavating a left part of the lower step about 6-8 meters behind the left part of the middle step or about 3-4 meters behind the right part of the middle step, and conveying excavated earthwork of the left part of the lower step out of the tunnel; (5) excavating a right part of the lower step about 3-4 meters behind the left part of the lower step, and conveying excavated earthwork of the lower step out of the tunnel; and (6) excavating the rest part of the tunnel bottom about 20-25 meters behind the right part of the lower step, excavating continuously according to the steps in a circulating and interlacing manner, and finally realizing tunnel excavating construction. The method can be used for building a large cross-section tunnel in a safe, rapid and economic manner.
Owner:CCCC SECOND HIGHWAY ENG CO LTD +1
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products