The invention discloses a construction process of an argilloid geological ground network. The construction process comprises the following steps of 1, material preparation and site preparation; 2, measurement, positioning and groove digging; 3, vertical grounding body laying; 4, horizontal grounding body laying; 5, grounding
system welding; 6, groove filling; 7, waterproof
processing during a grounding leading-up line penetrating through a
cushion layer; and 8,
grounding resistance measurement, in which the 50-by-6 galvanized flat steel horizontal grounding body with length larger than or equal to 6 meters, the 50-by-50-by-5 vertical grounding body in 2,500 millimeters, a 50-by-6 horizontal pressure-sharing belt, a 50-by-6 galvanized flat steel grounding leading-out line and resistance reduction agent are prepared, a corresponding construction operating surface is ensured, the leveling of a base is completed, and check and acceptance are performed according to bearing capability of foundation pit. By the process, the resistance is favorable reduced, the
corrosion-resistant capability is improved, the step
voltage can be reduced, the personal safety is improved, water prevention isfacilitated, the excavation area of a
plant is favorably reduced, and the construction cost is reduced.