The application discloses an electromechanical
construction management system and method based on an AI
algorithm, relates to the technical field of electromechanical
construction management, and is based on historical project data, analyzes installation sequence constraints between electromechanical modules, and constructs a
directed graph containing strong dependency relationships; analyzes the construction proficiency of each engineer on different electromechanical modules, and forms a personnel skill matrix; uses the
directed graph to simulate task progress and discrete events, outputs a comprehensive
bottleneck electromechanical module
list and corresponding construction period
delay risk value indicators; compares and simulates by virtually replacing engineers with different construction proficiency indicators, and screens implicit
bottleneck electromechanical modules; in new project construction, analyzes construction period execution deviation indicators, generates an early warning
signal and sends the early warning
signal to an administrator when the construction period execution deviation indicators continuously exceed a threshold value; and after the project ends, updates the personnel skill matrix by using actual installation data. The reliability and analysis accuracy of the model are improved.