The invention discloses a construction method of an integral overhanging structure compound road, which is suitable for steep mountainous areas, wherein reinforcement concrete columns and walls are cast along the road in certain interval, overhanging beams are arranged on the columns and are cast into one part with the columns and are fixed with the mountains, longitudinal beams and overhanging beams are cast into one part, a pre-made reinforcement concrete slab is laid on the overhanging part of adjacent overhanging beams and is cast into one part with the overhanging beams, the upper surface of the slab is laid on the
road surface, the overhanging mountain slope is laid on the reinforcement concrete
road surface to assist setting and construction. The construction process of the invention avoids deep
cut and high fill, forms road embankment by using whole-
casting retaining walls of columns and walls type within the road
bed range which is identified and stabilized, uses the overhanging structure to compensate the width-wanting parts of the road; ensures safety, reliability, endurance, reduces the damage on the
natural environment as much as possible, does least disturbance on the existing slopes, sustains the slopes self-stabilization, reduces construction quantity, lowers construction difficulty, saves occupancy area, and has good combined technical, economy and
social benefits.