The invention relates to the technical field of construction progress monitoring, in particular to a construction progress multi-dimensional
dynamic monitoring method based on
the Internet of Things and BIM, and the method comprises the following steps: obtaining a component number and a planned time period through the BIM, collecting an action
label, a three-dimensional coordinate and space projection matching time, and generating a component behavior set through
DBSCAN clustering; the method comprises the following steps:
slicing an action sequence to calculate frequency and coverage proportion; classifying component states to generate progress deviation; matching the deviation with a Hungary
algorithm to calculate a
coupling map; extracting a mechanical track and path included angle, normalizing and correcting the included angle to generate a deviation sequence, and grading track segments to generate a
dynamic monitoring index set. According to the method, time-space association is established based on component numbers and
coordinate projection, a classification model is constructed by using time slice coverage to identify progress deviation, task chain
coupling is analyzed through bidirectional matching, a deviation sequence is generated through included angle correction, a
delay amount and coverage rate
evaluation system is established, and progress deviation tracing and abnormal early warning are achieved.