The invention relates to a construction method of a long-distance box
culvert for shallow covering soil to penetrate through a
railway yard, which comprises the following steps: respectively constructing two working pits on two sides of an existing
railway line, and respectively prefabricating a box
culvert section in the two working pits; auxiliary beam structures are constructed at the corresponding positions of the existing
railway line where the two box
culvert sections are about to pass through, the auxiliary beam supporting structures carry out temporary overhead supporting on the existing
railway line, and each box culvert section is correspondingly provided with the corresponding construction auxiliary beam structure; the two box culvert sections are jacked, so that the two box culvert sections are in place; and a cast-in-place foundation pit is excavated at the
butt joint position between the two box culvert sections, the two jacked box culvert sections serve as access channels, and cast-in-place sequential connection of the two box culvert sections is completed in the cast-in-place foundation pit. The method has the advantages that under the condition that the railway operation is not interrupted, the shallow covering soil passes through the railway
station yard, the problems that the number of
station tracks is large, the distance is long, the risk is large, and the precision is high are solved, and a new thought and method are provided for urban roads to pass through the operating railway
station.