The invention discloses erecting equipment for a large-span half-through
arch bridge stretching across a
levee and a construction method. The erecting equipment comprises the steps that a
gantry crane anti-sliding foundation containing pre-embedded uplift piles and
saddle weights is constructed, a 120 t
gantry crane with hydraulic drive liftable supporting legs is adopted to be arranged across the
levee, and steel truss girders stretching to cover 16 sections of the Yifen side and 17 sections of the Chaohu side are erected; the included angle between the buckling
tower wind cable and the horizontal direction is optimized to be 60-65 degrees, and a PT100 temperature sensor is additionally arranged at an arch rib closure opening to achieve precise closure; the matched erecting equipment comprises the
gantry crane, a 100t arch climbing crane, a 400t. M
tower crane, a position adjusting
system and the like. By means of the structure and the method, the settlement amount of the
levee is controlled within 0.5 mm, the channel passing rate is 100%, the construction period is shortened by 32 days or above compared with an existing scheme, the cable buckling force is reduced by 20%, meanwhile, the construction method adapts to the wide
water level variable amplitude, is suitable for construction of the large-span half-through steel truss
arch bridge which crosses the river levee and needs to guarantee channel navigation, and has ecological protection and
engineering benefits.