The invention relates to the field of
building construction, in particular to an anti-leakage construction method for a post-cast strip of a
basement. The anti-leakage construction method for the post-cast strip of the
basement includes the steps of step 1, installing outer wall steel bars and an outer wall formwork part of the
basement, and constructing a fast-easy setback grid; step 2, preparingwater stop plates of the basement; step 3, arranging waterproof coatings on the outer walls and the
water stop plates of the basement; step 4, installing the
water stop plates on the outer walls anda bottom plate of the post-cast strip of the basement, and binding or
welding steel bars embedded in the
water stop plates and the outer wall steel bars of the basement; step 5, filling the gaps of the installed water stop plates with a filler for filling and leveling up treatment; step 6,
coating the surfaces of the water stop plates with waterproof
mortar, and manufacturing inner corner parts into an arc angle shape; and 7, carrying out integral waterproof construction on the outer walls of the basement, repairing the gaps, arranging protective
layers on the outer sides of the waterproof coatings, then carrying out backfilling, and completing anti-leakage construction of the post-cast strip of the basement.