Patents
Literature
Hiro is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Hiro

33 results about "Wall slip" patented technology

Concrete silo inner lining steel rail and warehouse wall slip form integrated construction method

The invention discloses a construction method for integration of a concrete silo internal lining steel rail and a silo wall slip form. The method comprises the following steps: when the height of the internal lining steel rail is reached to the limestone silo construction according to design requirement, a silo wall inner formwork of the slip form is removed, and a ring steel plate is arranged at the design height of the silo inner side; effective number of steel rails are vertically arranged on the ring steel plate, and connected with one another through reinforcement steel bars, and the steel rails are welded with anchoring reinforcement steel bars connected with the silo wall reinforcement steel bars; after the position, distance and verticality of the steel rails are corrected, the joints between the reinforcement steel bars and the steel rails are welded; and the anchoring reinforcement steel bars and the silo wall reinforcement steel bars are tightly bound and arranged on the silo wall inner formwork again, and the concrete is continuously cast between the silo and the steel rails until the design height of the silo is reached, thereby improving the wearing resistance of the silo, prolonging the service life of the limestone silo by 15 to 20 years, reducing manpower consumption by 110 working days, reducing material consumption by 30,000 yuan, saving the time of welding, arrangement and secondary casting of the steel rails and shortening construction period by 30 days.
Owner:河北省第四建筑工程有限公司

Single-side side wall slip form and construction method

Disclosed are a single-side slide wall slip form and a construction method thereof. The slip form is composed of form plates, lifting frames, back ridges, platforms, back connectors, a guide rail, guide wheel mechanisms, hydraulic jacks, limiting levelers, climb poles and a tube frame by bolt connection. Webs welded on a face plate of each form plate are provided with bolt holes and are suspended on the back ridges which are in channel shapes and made of steel, and thirty four form plates are connected to form a 30m high form plate set which inclines by 0.3%-0.5%. Each lifting frame is made of steel channels and steel angles by connecting. The back connectors are steel plates. The form plates, the platforms and the back connectors are integrally connected with the lifting frames, and are connected with the hydraulic jacks to drive the slip form to ascend. The lifting frames are fixedly connected with the lower back ridges through diagonal braces. The guide rail is made of steel channels and connected with rock anchor bolts by welding. Each guide wheel mechanism comprises guide wheels, a support and shafts and is mounted between the back ridges, and the support is connected with the guide rail through the shafts. The climb poles are made of steel tubes and fixed, and the jacks climb along the climb poles. The limiting levelers are used for adjusting climbing position. The tube frame is used for guaranteeing stable climbing. The construction method includes: casting when the slip form climbs, and concreting once.
Owner:SINOHYDRO BUREAU 14 CO LTD

Tube structure roof panel construction method and hanger formwork system

The invention discloses a tube structure roof panel construction method. The method comprises the steps of 1, building a tube structure with a slip-form construction method, and arranging an embedded ring at the top end of a tube wall; 2, splitting a slip form inner frame and a slip form outer frame and lowering the slip form inner frame to be below the elevation of a roof panel after tube wall slip-form construction; 4, fixedly connecting the slip form inner frame with the embedded ring with a steel wire rope, and then making the slip form inner frame fixed relative to the inner wall of a tube body; 5, laying planks and steel channels on the slip form inner frame, and conducting support frame erection and roof construction. The invention further discloses a construction system. According to the roof panel construction hanger formwork system, the slip form inner frame is transformed into a hanger formwork to serve as a support platform of a roof panel support frame, so that roof panel construction is conducted; a pull-up reinforcing mode is adopted for the hanger formwork, the hanger formwork and the embedded ring at the top end of the tube wall are connected through the steel wire rope on the upper portion, the hanger formwork abuts against the tube wall through a U-shaped support, swing of a frame body is effectively prevented, the using range and using time of the hanger formwork system are widened and prolonged, construction difficulty is reduced, construction period is shortened, danger coefficient is reduced, and construction cost is saved.
Owner:MCC TIANGONG GROUP

An Evaluation Method of Fault Sealing

The invention relates to a method for evaluating the fault sealing property in the technical field of oil and gas field exploration. The method includes the steps of (1) selecting a breakpoint in needof sealing property evaluation on a fault that is dislocated in a reservoir stratum, determining each sand-mud stratum with relative wall slip through the breakpoint, and determining the thickness [delta]Zi of each sand-mud stratum; (2) sequentially acquiring the shale content Vshi of each sand-mud stratum slipping through the breakpoint; (3) sequentially solving for a weighting coefficient Wi slipping through each sand-mud stratum; (4) calculating a weighted mudstone fault mud ratio WSGR value of the breakpoint; and (5) evaluating the sealing property of the reservoir at the breakpoint location by using the weighted mudstone fault mud ratio WSGR value, when the WSGR value is greater than or equal to 0.6, indicating that the fault sealing property of the breakpoint location is good and the oil and gas can be effectively sealed, determining the reservoir stratum as an oil stratum or an oil-bearing water stratum with a large probability, and determining the reservoir stratum as a waterstratum with a large probability otherwise. The method fully considers the docking relationship between the two walls of the fault, adds the distance coefficient to reflect the contribution degree ofeach relative wall point on the calculation point, and improves the accuracy and precision of the judgment of the fault sealing property.
Owner:CHINA PETROLEUM & CHEM CORP +1

Cast-in-situ lightweight aggregate concrete filler wall slip-form construction template system and construction method

The invention discloses a cast-in-situ lightweight aggregate concrete filler wall slip-form construction template system and a construction method. The template system comprises an outer mold and an inner mold, wherein the outer mold comprises an outer mold frame and a first mirror multilayer board connected to the outer mold frame; reinforced angle iron is welded at the left side and the right side of the outer mold frame; inverse L-shaped round steel is arranged beside the reinforced angle iron; a first hook ring is welded at the top of the outer mold frame; the inner mold comprises a sealed inner mold body; a vibrator is arranged inside the inner mold body; two inner mold support handles are symmetrically arranged at two sides of the top of the inner mold body. The method comprises the following steps: 1, fabricating the outer mold and the inner mold; 2, mounting the outer mold; 3, installing the inner mold; 4, reinforcing and correcting the outer mold; 5, casting and vibrating lightweight aggregate concrete; 6, lifting the template system; 7, repeating the steps 5 to 6 for a plurality of times and casting until the distance from the template system to an original structure body is 150mm-250mm; and 8, stripping the mold. A constructed wall body disclosed by the invention is good in integrality, stable and reliable in strength, and free of construction waste, and the labor cost is greatly reduced.
Owner:SCEGC NO 5 CONSTRUCTION ENGINEERING GROUP COMPANYLTD

Construction method of compound single-side formwork system for basement exterior wall

ActiveCN111119237BImprove connection strengthReduce the difficulty of connection positioningArtificial islandsCellarsSupporting systemArchitectural engineering
The invention relates to a construction method of a composite single-side formwork system for an outdoor wall of a basement, comprising the steps of: 1) construction preparation; 2) layout of a transverse support waist beam; 3) construction of a prefabricated tire formwork support; 4) formwork support at the bottom of an outdoor wall of a basement; 5) Concrete pouring construction of the basement exterior wall; 6) Sliding formwork construction of the basement exterior wall. The beneficial effects of the present invention are: the pile side hoop plate and the support pile are connected through the connecting anchor bolt and the hoop plate anchor bar, and the transverse brace waist beam is connected with the pile side hoop plate through the waist beam hoop, which reduces the difficulty of component connection. The integrity of the structure is improved; at the same time, the present invention arranges the first connecting hoop and the second connecting hoop at the longitudinal junction of the cross support waist beam, and the outer wall of the first connecting hoop and the second connecting hoop Auxiliary tie bars are set between the tie support plates, which can effectively improve the connection strength of the cross brace waist beam and reduce the difficulty of connection positioning.
Owner:华中伟业建设集团有限公司

Reinforced concrete silo top plate formwork construction method

The invention relates to a reinforced concrete silo roof formwork construction method which comprises the following steps: after silo wall slip form construction is completed, descending a slip form platform to a preset elevation for the first time and then reinforcing the slip form platform to serve as a roof formwork supporting platform for silo roof construction; and after construction of the silo top plate is completed, the slip form platform descends to the ground for the second time, and the slip form platform is overall dismantled. And the lowered and fixed slip form platform is used as an operation platform for dismantling the slip form lifting frame and the template, so that the workload and the safety risk of hoisting on the top surface of the vertical silo are reduced. The slip form platform serves as a supporting point and a working face for supporting the silo top plate formwork, the construction process is simple, operation is convenient, cost is reduced, and the construction progress is accelerated. The slip form platform is disassembled on the ground after descending for the second time, operators do not need to work high above the ground, the risk of working high above the ground is greatly reduced, and the safety degree of construction work is improved.
Owner:CHINA CHEM ENG SECOND CONSTR

Concrete silo inner lining steel rail and warehouse wall slip form integrated construction method

The invention discloses a construction method for integration of a concrete silo internal lining steel rail and a silo wall slip form. The method comprises the following steps: when the height of the internal lining steel rail is reached to the limestone silo construction according to design requirement, a silo wall inner formwork of the slip form is removed, and a ring steel plate is arranged atthe design height of the silo inner side; effective number of steel rails are vertically arranged on the ring steel plate, and connected with one another through reinforcement steel bars, and the steel rails are welded with anchoring reinforcement steel bars connected with the silo wall reinforcement steel bars; after the position, distance and verticality of the steel rails are corrected, the joints between the reinforcement steel bars and the steel rails are welded; and the anchoring reinforcement steel bars and the silo wall reinforcement steel bars are tightly bound and arranged on the silo wall inner formwork again, and the concrete is continuously cast between the silo and the steel rails until the design height of the silo is reached, thereby improving the wearing resistance of thesilo, prolonging the service life of the limestone silo by 15 to 20 years, reducing manpower consumption by 110 working days, reducing material consumption by 30,000 yuan, saving the time of welding,arrangement and secondary casting of the steel rails and shortening construction period by 30 days.
Owner:河北省第四建筑工程有限公司

Double-cylinder-wall concrete silo slip form construction operation platform and construction method

The invention discloses a double-cylinder-wall concrete silo slip form construction operation platform and a construction method. The double-cylinder-wall concrete silo slip form construction operation platform comprises an outer cylinder wall lifting system and an inner cylinder wall lifting system which are synchronously lifted, wherein the outer cylinder wall lifting system and the inner cylinder wall lifting system each comprise an inner side platform and an outer side platform, each of the inner side platforms and the outer side platforms comprises an upper layer, a middle layer and a lower layer, and the three layers of platform bodies on the outer side of the inner cylinder wall and the three layers of platform bodies of the inner side of the outer cylinder wall are correspondinglyconnected into a whole; and the upper-layer platform bodies are used for temporarily stacking slip form construction materials, the middle-layer platform bodies are used for steel bar binding, concrete transportation and pouring and tamping space, and the lower-layer platform bodies are used as a platform for receiving light, maintaining and checking after concrete is out of the forms. The three layers of platform bodies are reasonable in work division, and the requirement for slip form simultaneous lifting of a double-cylinder-wall silo is effectively met. By means of the double-cylinder-wallconcrete silo slip form construction operation platform and the construction method, the inner cylinder wall and the outer cylinder wall are connected into the whole on the basis of an original single-cylinder-wall slip form, so that the overall stability of a slip form system is improved, the slip form is lifted through the double cylinder walls at the same time, and the construction period is greatly shortened.
Owner:MCC5 GROUP CORP SHANGHAI

A curtain wall air tightness detection device and detection method thereof

The invention relates to a curtain wall air tightness detection device, which includes a pressure box, a pressure supply component and a measurement component; the pressure box includes an outer box that fits on the surface of the curtain wall and an inner box that is arranged in the outer box and fits on the surface of the curtain wall body, the outer wall of the inner box perpendicular to the surface of the curtain wall and the inner wall of the outer box perpendicular to the surface of the curtain wall are slidingly matched and sealed; the surface of the inner box and the curtain wall is fixed with a first sealing ring around the opening of the inner box , the surface of the outer box and the curtain wall is fixed with a second sealing ring around the opening of the outer box; the outer box is provided with a mounting piece fixed to the beam; the pressure supply component includes an air pump and an air pipe, and the outer box is parallel Between the inner side wall of the curtain wall and the outer side wall of the inner box body parallel to the curtain wall, there are control valves communicating with the outer box body and the inner box body respectively, and the gas pump communicates with the control valve. The invention has the effect of good airtightness, and improves the detection accuracy of the airtightness of the curtain wall.
Owner:深圳市恒义建筑技术有限公司

Cast-in-place lightweight aggregate concrete filled wall slipform construction formwork system and construction method

The invention discloses a cast-in-situ lightweight aggregate concrete filler wall slip-form construction template system and a construction method. The template system comprises an outer mold and an inner mold, wherein the outer mold comprises an outer mold frame and a first mirror multilayer board connected to the outer mold frame; reinforced angle iron is welded at the left side and the right side of the outer mold frame; inverse L-shaped round steel is arranged beside the reinforced angle iron; a first hook ring is welded at the top of the outer mold frame; the inner mold comprises a sealed inner mold body; a vibrator is arranged inside the inner mold body; two inner mold support handles are symmetrically arranged at two sides of the top of the inner mold body. The method comprises the following steps: 1, fabricating the outer mold and the inner mold; 2, mounting the outer mold; 3, installing the inner mold; 4, reinforcing and correcting the outer mold; 5, casting and vibrating lightweight aggregate concrete; 6, lifting the template system; 7, repeating the steps 5 to 6 for a plurality of times and casting until the distance from the template system to an original structure body is 150mm-250mm; and 8, stripping the mold. A constructed wall body disclosed by the invention is good in integrality, stable and reliable in strength, and free of construction waste, and the labor cost is greatly reduced.
Owner:SCEGC NO 5 CONSTRUCTION ENGINEERING GROUP COMPANYLTD

A Method of Determining the Depth of Sliding Slabs in Coal Wall and Its Slipping Risk

The invention discloses a method for determining the depth and slip risk of a coal wall slip sheet. The method includes assuming n circle centers of heights yi (i = 1, 2, 3,..., n) far from a top plate and n slip arc radius Rj (j = 1, 2, 3,..., n), defining n*n slip surface Sij according to the yi and Rj, and figuring out a risk coefficient Kij; acquiring a slip risk coefficient curved surface K of the n*n slip surface Sij, and acquiring a curve Kcr=1 by means of the intersection of a plane K=1 and the curved surface K; defining the slip surface depth d as the distance between the intersection of the slip surface and top plate and a coal wall, acquiring a curved surface of the slip surface depth d of the n*n slip surface Sij, and acquiring a curve of a critical slip depth dcr by projecting the curve Kcr = 1 to the curved surface d; figuring out a maximum value dcrmax (ycr, Rcr) of the curve dcr, determining a slip surface as the maximum depth critical slip surface according to the ycr and Rcr, and allowing the value dcrmax to be the depth of the coal wall slip sheet. The method is used for designing and developing control implementation and parameters of the coal wall slip sheet according to the depth during the coal wall management of working face with large mining height.
Owner:TAIYUAN UNIV OF TECH
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products