The invention relates to the technical field of flexible direct-current
power transmission, in particular to an insulation coordination method of an extra-
high voltage flexible direct-current converter
station connected to a
new energy base, which comprises the following steps of: S1, analyzing a
lightning arrester configuration scheme and selecting parameters according to a
system main wiring form and an
overvoltage characteristic of the converter
station; s2, establishing an electromagnetic transient
simulation model of the internal
overvoltage of the large-scale
new energy delivery system, establishing an actual control protection strategy, and establishing a high-frequency transient model of the
lightning overvoltage of the extra-
high voltage flexible
DC converter station connected to the
new energy base; s3, internal overvoltage
simulation is carried out, and an insulation cooperation scheme is adjusted according to a
simulation result; and S4, carrying out
lightning verification based on the
alternating current side intrusion wave and the
direct current side lightning intrusion wave. Through reasonable
lightning arrester configuration and parameter optimization, insulation cooperation of the
system is realized, influence of transient overvoltage on equipment is effectively reduced, efficient and stable operation of the
system is ensured, and equipment cost and
engineering construction cost are reduced at the same time.