Patents
Literature
Hiro is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Hiro

44results about How to "Low demolition cost" patented technology

Incremental launching construction method for large-span steel box girder spanning constructed road

The invention discloses an incremental launching construction method for a large-span steel box girder spanning a constructed road. An incremental launching steel box girder spans the constructed road, is supported by five permanent buttresses, and is formed by a plurality of steel box girder segments which are spliced back to front; the five permanent buttresses are all uncovered girder double-cylinder pillars; the uncovered girder double-cylinder pillars respectively consist of two cylindrical buttresses which are supported below the left side and the right side of the steel box girder; the incremental launching construction method for the incremental launching steel box girder comprises the following steps: I, splicing jig frames; II, constructing temporary buttresses and rigid brackets; III, splicing the steel box girder and mounting guide beams; IV, mounting an incremental launching device and a second longitudinal slideway beam; V, performing incremental launching. The method disclosed by the invention is simple in step, reasonable in design, simple and convenient to construct and good in use effect, and by constructing the rigid brackets on the outer sides of the buttresses and mounting a longitudinal slideway and a transverse deviation correcting device, the incremental launching construction of the large-span steel box girder can be easily, conveniently and rapidly completed.
Owner:THE NO 6 ENG CO LTD OF CHINA RAILWAY 20TH BUREAU GRP

Deep foundation pit support and removing method thereof

The invention provides a deep foundation pit support and a removing method of the deep foundation pit support, and belongs to the field of building construction. The deep foundation pit support comprises a plurality of sections of concrete cubic blocks and a plurality of reinforcing steel bars. Every two adjacent concrete cubic blocks are bonded through a sulphide mastic interlayer. The reinforcing steel bars penetrate through the concrete cubic blocks and the sulphide mastic interlayers. An electric heater is pre-buried in each sulphide mastic interlayer. The removing method of the deep foundation pit support comprises the steps of (1) starting the electric heaters to heat the sulphide mastic interlayers, (2) when the sulphide mastic interlayers are heated to become soft, removing the sulphide mastic interlayers to expose the reinforcing steel bars penetrating through the adjacent concrete cubic blocks, (3) cutting off the reinforcing steel bars between the adjacent concrete cubic blocks to enable the adjacent concrete cubic blocks to be mutually separated, and (4) lifting out the concrete cubic blocks from a deep foundation pit. When the deep foundation pit support and the removing method of the deep foundation pit support are used, the removing cost of the deep foundation pit support can be effectively reduced on the premise that the removing efficiency and environmental protection are kept.
Owner:NO 2 CONSTR GRP CO LTD OF SHANGHAI CONSTR GRP

Pumped storage power plant tail water retained rock step blasting safety protection method

The invention discloses a pumped storage power plant tail water retained rock step blasting safety protection method, and relates to an underwater rock step blasting safety protection method. A bladder curtain and porous stoplog gates are constructed outside a rock step to be blasted; the bladder curtain consists of a plurality of steel pipes; two rows of holes are bored on each steel pipe; and each steel pipe is connected with an air pipe of an air compressor. The porous stoplog gates consist of a steel frame and bamboo rafts; I sections are arranged on both sides of the stoplog gate of eachhole; the two sides of each I section are fixed on round flow splitting support piers through steel plates and expansion bolts; each stoplog gate is in welded connection through channel steel, the I sections and angle bars; a layer of vertical bamboo gangway is spread on the water inlet surfaces of the stoplog gates; and simultaneously safety nets are arranged on the tops of flow splitting support piers on the top and both sides of a single hole stoplog gate. The method adopts the proposal of arranging the bladder curtain plus the steel frame, the bamboo rafts and the safety nets to replace aproposal of the stoplog gate, has scientific and reasonable design, protects a trash rack and a tail gate against the damage and the influence of the blasting, and brings about easy spoil removal, short manufacturing and installation time limits, and low manufacturing, installation and demolition cost.
Owner:STATE GRID CORP OF CHINA +2

Soil pressure balancing method

The invention discloses a soil pressure balancing method. The problems that in the jacking pipe operation process, over-excavation and under-excavation may happen when a face earthwork is excavated, a surrounding soil body is likely to be disturbed, the road on the ground is damaged, a building sinks and deforms, and an underground pipeline is broken are solved. According to the technical scheme, the soil pressure balancing method is characterized by comprising the following steps that firstly, construction preparation is made; measuring and setting-out are conducted; thirdly, equipment is arranged in a work well; fourthly, wall penetrating hole treatment is conducted; fifthly, jacking pipe equipment is installed; sixthly, a jacking pipe penetrates out of a wall penetrating hole; seventhly, pipeline installation is conducted; eighthly, jacking is conducted; ninthly, the jacking pipe enters the hole; tenthly, a tool pipe is taken out; and eleventhly, hole treatment is conducted. By means of the soil pressure balancing method, over-excavation and under-excavation generated when the face earthwork is excavated are reduced, the disturbance to the surrounding soil body is reduced, the damage to the road on the ground is reduced, and meanwhile the phenomena that the building sinks and deforms and the underground pipeline is broken are reduced.
Owner:天鸿建设集团有限公司

Heatable fluid line, use thereof and method for producing same

The invention relates to a heatable fluid line (1) comprising at least one pipeline (2, 218) and at least one electrical heating conductor (3, 224) extending over at least a partial section of the length (L) of the pipeline. In order that the fluid line (1) fulfills increased requirements in respect of resistance to high temperatures, compensation of pressure pulsations and/or compression resistance, while being less complex to produce and assemble and/or connect, according to the invention the pipeline (2, 218) has at least two longitudinal sections (2a, 202, 2b, 204) which are designed differently in respect of the material properties and/or design thereof, namely at least one first longitudinal section (2a, 202) which consists of a first material which comprises a first polymer and a second longitudinal section (2b, 204); which consists of a second material which comprises a second polymer, wherein the material of the second longitudinal section (2b, 204) is more flexible and/or has a higher resilience than the material of the first longitudinal section (2a, 202). The described method for producing such a fluid line according to the invention relates to an adaptive attachment of the heating conductor (3, 224) on the outside of the pipeline (2, 218) which permits the heating conductor (3, 224) to be wound around fluid coupling and/or connector parts, in particular the housings thereof (14, 15, 16, 17, 21, 22, 33, 34, 50, 51, 52, 53, 206, 208, 210, 212, 230, 232, 244, 246) by means of which the line (1) is assembled, without strand separation.
Owner:VOSS AUTOMOTIVE

Energy saving and emission reduction transformation method for transforming cement cyclone preheater kiln into outside-kiln precalcining kiln

The invention discloses an energy saving and emission reduction transformation method for transforming a cement cyclone preheater kiln into an outside-kiln precalcining kiln. A tertiary air duct (07), an offline calcining combustor (08), a calcining combustor burner (09), a five-stage preheater (10), a fresh air high-temperature fan (11), a normal temperature gas analyzer (12), a tertiary air gate valve (13) and a high temperature gas analyzer are newly built on the basis of an original cyclone preheater rotary kiln line, wherein a new preheater system and an old preheater system serve cement production jointly. The original kiln shutdown duration of eight months is shortened to 2-3 months, the cost of detaching of an old preheater is reduced, raw materials of the old preheater are wholly conveyed into the offline calcining combustor, the in-kiln calcining rate of the raw materials is increased to 90% or over from original 100% of in-kiln calcining through the offline calcining combustor, and the raw materials of the new preheater enter the kiln through an original feed-end chamber. After the cyclone preheater kiln is transformed into the precalcining kiln, 100% of fuel of a kiln head is reduced to 40%, the amount of NOx generated by the kiln head at a high temperature environment is reduced, and the method can quickly change the cement production process and achieve the yield increase, energy saving and emission reduction effects for a cement sintering system.
Owner:BEIJING TRIUMPH INT ENG

Soft soil stratum subway station expansion method and structure based on inserted beam freezing method

The invention provides a soft soil stratum subway station expansion method and structure based on an inserted beam freezing method. The soft soil stratum subway station expansion structure comprises shield tunnels, a middle platform connected between the two parallel shield tunnels and communicating with the shield tunnels, and frozen soil layers wrapping the outer side of the middle platform; themiddle platform comprises a top lining unit, a bottom lining unit, side columns and a structural bottom plate, the top lining unit and the bottom lining unit are arranged between the shield tunnels and are symmetrical up and down, and the frozen soil layers are distributed along the arched outer surfaces of the top lining unit and the bottom lining unit; the two side ends of the bottom lining unit and the two side ends of the top lining unit are connected and supported through the side columns; and the structural bottom plate is arranged above the bottom lining unit and is kept on the same horizontal plane with the two ends of the bottom lining unit. The method solves the problem of large deformation of subways and surrounding soil caused by serious soil moving in an expansion mode, and has the advantages of being high in construction efficiency, short in construction period and high in safety.
Owner:SHIJIAZHUANG TIEDAO UNIV +1

Method for dismantling discarded jacket through air bags

A method for dismantling a discarded jacket through air bags comprises the following steps: 1, dismantling preparation is performed on the discarded jacket; 2, a plurality of air bag groups are lowered into water and are connected to form a whole air bag floating aiding unit; 3, the air bag floating aiding unit and a local control panel arranged at the top of the discarded jacket are connected, so that the remote control panel can realize controlling and monitoring functions; 4, the air bag floating aiding unit is inflated to be in a pressure maintaining state; 5, a workboat is connected with the discarded jacket and tows the discarded jacket away from the site. The method has the advantages that the dismantling efficiency can be improved greatly and the dismantling cost is reduced; the offshore construction risks are reduced; meanwhile, the completeness of the discarded jacket can be kept, the construction risks caused by jacket disassembly are reduced, and the air bags are recyclable, so that the engineering cost can be reduced substantially.
Owner:CHINA NAT OFFSHORE OIL CORP +1

Construction method of large-height small-sized cast-in-place concrete beam slab

The invention discloses a construction method of a large-height small-sized cast-in-place concrete beam slab. The large-height small-sized cast-in-place concrete beam slab comprises a floor foundation built by using multiple layers of floor slabs and a concrete framework column. The method comprises the following steps of: preserving a bolt hole on a concrete framework column which is opposite to a lower layer slab of the floor on which a concrete beam slab is required to be poured; arranging a channel steel support beam between the lower layer slab of the floor on which the concrete beam slab is required to be poured and the preserved bolt hole, and connecting and fixing the two ends of the support beam by using bolts; arranging a steel wire rope on the middle part of the support beam, and fixing the other end of the steel wire rope on a hoisting ring embedded into the floor on which the concrete beam slab is required to be poured; building a template support beam on the support beam; fixedly arranging a template on the template support frame; building a protective net; and pouring. Due to the adoption of the construction method, the building height of a scaffold is reduced greatly, a large quantity of frame pipes and fasteners are saved, and material cost, manual installation cost and detaching cost are reduced.
Owner:河北省第二建筑工程有限公司

Rotation V-type T-structure bridge pier and construction thereof

The invention relates to a rotation V-type T-structure bridge pier and a construction thereof. When an included angle formed between a line and an existing busy trunk line through vertical crossing is smaller, cross-hole arrangement of a bridge is more difficult. The bridge pier is constructed on one side of the existing trunk line, and comprises a pile foundation, a supporting platform, pier arms and a cover beam from bottom to top, wherein the supporting platform is divided into a lower rotary table and an upper rotary table from bottom to top; a rotary spherical hinge is arranged between the upper rotary table and the lower rotary table; during line operation skylight time, the upper rotary table and the structure rotate to a designed position by taking the rotary spherical hinge as the center, concrete on the outer side of the rotary spherical hinge is poured to form a solid stage, and the lower rotary table and the upper rotary table are fixedly connected together to complete construction. Due to the adoption of a rotation V-type T-structure scheme, the construction only needs to be performed on one side of the existing line, requirements for roads and construction sites on the other side are reduced, the conditions that houses on two sides of the existing line in an urban area are dense and are difficult to remove are facilitated, the removal cost is greatly reduced, and the construction period is guaranteed; meanwhile, due to the adoption of rotation construction, the influence on operation of the existing line is minimized.
Owner:CHINA RAILWAY FIRST SURVEY & DESIGN INST GRP

Center joint fixed member for fabricated integrated wall tile system and assembly method thereof

The invention discloses a center joint fixed member for a fabricated integrated wall tile system and an assembly method thereof, and relates to the technical field of installation methods of fabricated wall tiles. The center joint fixed member for the fabricated integrated wall tile system and the assembly method thereof solve the problems that an existing wet pasting method of the wall tiles haspoor working environment, long construction period and high labor cost, and workers are susceptible to pneumoconiosis; and an existing dry hanging method of the wall tiles has cumbersome installation,high labor and material costs, large space occupied by keels on the back portions of the wall tiles and reduced utilization rate of indoor space. Vertical members are positioned at internal and external angles of a wall, an L-shaped clamping piece is mounted on each pair of longitudinal fish-scale-shaped punching holes of the vertical members in a clamped mode, and a plurality of transverse members I are arranged between every two adjacent vertical members. Clamping slots matched with first supporting ends and second supporting ends of the transverse members I are formed in the upper and lower end surfaces of the wall tiles correspondingly, and the wall tiles are mounted on every two adjacent transverse members I. The center joint fixed member of the fabricated integrated wall tile systemand the assembly method thereof are used for fabricating the fabricated integrated wall tile system.
Owner:王圣保

Umbrella skirt type cement-based composite insulated cross arm and manufacturing technology thereof

The invention discloses an umbrella skirt type cement-based composite insulated cross arm. The umbrella skirt type cement-based composite insulated cross arm is of a triangular outline structure and is formed in the manner that three cement-based composite insulated components and three rigid components are connected through flanges. Power fitting strings are hung at the ends of the insulated cross arm. The cement-based composite insulated components are manufactured in a one-time forming manner through a centrifugal process. Besides, an umbrella skirt structure is formed on the surface of each cement-based composite insulated component in a one-time manner. In this way, the umbrella skirt type cement-based composite insulated cross arm has not only the insulated function but also the characteristics of a supporting structure and can replace an insulator and a steel cross arm which are adopted in a transmission line iron tower formerly, the umbrella skirt type cement-based composite insulated cross arm can reduce the line corridor distance and the height of the iron tower under the condition of meeting the use requirements of cross arms of extra-high-voltage transmission line iron towers, ultra-high-voltage transmission line iron towers and high-voltage transmission line iron towers, and therefore the operation cost of transmission lines can be effectively reduced.
Owner:CHANGSHU FENGFAN POWER EQUIP

Pumped storage power plant tail water retained rock step blasting safety protection method

The invention discloses a pumped storage power plant tail water retained rock step blasting safety protection method, and relates to an underwater rock step blasting safety protection method. A bladder curtain and porous stoplog gates are constructed outside a rock step to be blasted; the bladder curtain consists of a plurality of steel pipes; two rows of holes are bored on each steel pipe; and each steel pipe is connected with an air pipe of an air compressor. The porous stoplog gates consist of a steel frame and bamboo rafts; I sections are arranged on both sides of the stoplog gate of each hole; the two sides of each I section are fixed on round flow splitting support piers through steel plates and expansion bolts; each stoplog gate is in welded connection through channel steel, the I sections and angle bars; a layer of vertical bamboo gangway is spread on the water inlet surfaces of the stoplog gates; and simultaneously safety nets are arranged on the tops of flow splitting support piers on the top and both sides of a single hole stoplog gate. The method adopts the proposal of arranging the bladder curtain plus the steel frame, the bamboo rafts and the safety nets to replace a proposal of the stoplog gate, has scientific and reasonable design, protects a trash rack and a tail gate against the damage and the influence of the blasting, and brings about easy spoil removal, short manufacturing and installation time limits, and low manufacturing, installation and demolition cost.
Owner:STATE GRID CORP OF CHINA +2

Transverse integral component for assembled integrated wall-tile system and assembling method thereof

The invention discloses a transverse integral component for an assembled integrated wall-tile system and an assembling method thereof, and relates to the field of wall-tile processing, assembled devices and assembling installing technologies. By means of the transverse integral component for the assembled integrated wall-tile system and the assembling method thereof, the problems that in an existing wall-tile wet combining method, the work environment is poor, the construction period is long, the labor cost is high, and workers are subject to pneumoconiosis are solved; the problems that in anexisting wall-tile dry hanging method, installing is tedious, the labor cost and the material cost are high, occupied space of wall-tile back fitting keels is large, and the using rate of indoor spaceis reduced are solved. According to the transverse integral component for the assembled integrated wall-tile system and the assembling method thereof, vertical components are fixedly connected with wall corners, a clamping piece I is clamped on every pair of longitudinal scale punched holes of a vertical component, multiple transverse components I are arranged between the two adjacent vertical components, elastic protection films are arranged on the backs of wall tiles, each wall tile is installed between the two adjacent transverse components I, and clamping grooves in the upper end face andthe lower end face of each wall tile are matched with a first hook and a second hook of the corresponding transverse component I respectively. The transverse integral component for the assembled integrated wall-tile system and the assembling method thereof are used for assembling of an assembled integrated wall-tile system.
Owner:王圣保

Vertical shaft excavation construction method adopting mode of downhole soil outlet and feeding

InactiveCN107893659AReduce construction site areaSolve the demolition problemShaft liningUnderground spaceEngineering
The invention discloses a vertical shaft excavation construction method adopting a mode of downhole soil outlet and feeding. The vertical shaft excavation construction method comprises the following steps that a vertical shaft hole and a construction channel are constructed in a construction site, and the bottom of the vertical shaft hole is made to communicate with an existing underground space through the construction channel; a vertical shaft is excavated outside the vertical shaft hole from top to bottom; soil masses generated in vertical shaft excavation are made to pass through the vertical shaft hole and the construction channel sequentially and then transported out from an existing vertical shaft arranged in the underground space; and in the vertical shaft excavation process, firstly, the top of the vertical shaft is excavated, an opening locking ring is constructed, then, the vertical shaft continues to be excavated downwards, meanwhile, concrete mixed materials are made to pass through the existing vertical shaft, the underground space and the construction channel sequentially and then transported to the bottom of the vertical shaft hole, and a concrete retaining wall isconstructed for the shaft wall of the excavated part, located below the opening locking ring, of the vertical shaft through a shotcrete anchorage machine arranged at the bottom of the vertical shaft hole. The area of the construction site is decreased greatly, the demolition problem is solved, and the phenomenon of resident disturbance caused by demolition, noise, dust, road occupation and the like is reduced.
Owner:SUBWAY ENG CO LTD OF CHINA RAILWAY 16TH CONSTR BUREAU +2

Bridge resetting bracket and bridge resetting method

The invention belongs to the technical field of bridge construction, and discloses a bridge resetting support and a bridge resetting method. The bridge resetting support comprises a first bearing platform, a first supporting frame, jacking devices, a lifting device, a suspension device and a horizontal position adjusting device. The first bearing platform is arranged at the bottom end of the pier column, a preset hole penetrating through the first bearing platform in the height direction of the first bearing platform is formed in the middle of the first bearing platform, and the pier column penetrates through the preset hole. The first supporting frames are arranged on the first bearing platform, and the first supporting frames are arranged on the two sides of the pier column. The jacking devices are arranged at the top ends of the first supporting frames. The lifting device is arranged at the top end of the T-beam. The suspension device comprises a joist and a connecting piece, the joist is arranged at the bottom end of the cover beam, the bottom end of the connecting piece is connected with the joist, and the top end penetrates through the T beam to be connected with the lifting device. When the bridge is reset, the pier column and the bent cap do not need to be dismantled and rebuilt, construction cost and safety risks are reduced, working hours are reduced, and the requirement for emergency construction can be better met.
Owner:ROAD & BRIDGE EAST CHINA ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products