The invention relates to an incremental launching construction method applied to a variable-height curve beam, which comprises the following steps of: controlling a walking type incremental launching
system to jack up a beam body firstly through a multi-linkage
intelligent control system, then moving forwards and falling down, then supporting by a vertical variable-height
supporting system, and then continuously jacking up the beam body by the walking type incremental launching
system; at the moment, the beam height of the beam body changes along the pushing longitudinal path, after the beam body falls down, the jack of the vertical height-variable
supporting system correspondingly descends at the corresponding position, and the balance of the main beam is maintained. And meanwhile, a vertical lifting system and a transverse deviation correction force
transmission system of the transverse deviation correction device apply different horizontal forces to the main beam along with advancing of the pushing, transverse deviation correction of the curve beam is completed, coordinate programs are set in advance in the whole process,
automatic control is achieved, and therefore intelligent pushing operation of the whole variable-height curve steel box beam is completed. The large-span variable-height curve
steel box girder incremental launching construction method has the advantages that incremental launching construction of the large-span variable-height curve