The invention belongs to the technical field of
railway signal construction. In order to solve the technical problems of serious crossing of various cables,
chaotic construction procedures, long construction period and low work efficiency in the existing
railway signal indoor construction, a method for improving the construction process of the
railway signal indoor is provided. Including the following steps: Step 1, indoor cabinet
layout, Step 2, planning cable routing, drawing a construction
path diagram of cable routing, Step 3, installing cable brackets, Step 4, indoor cable
layout and fixing, Step 5, tidying up Factory wiring, arranging the cables from the computer room to the console, step 6, installing the
cable tray, step 7, cable introduction, step 8, first-time termination and cable fixing, step 9, second-time termination and cable fixing, steps 10. The cable is connected to the
lightning protection distribution cabinet, step 11, indoor equipment
lightning protection and grounding, step 12, laying indoor
copper foil, step 13, laying static floor, indoor signs. The invention improves construction efficiency and saves construction cost.