The invention discloses a constructing method for a continuous bearing layer of a super long socketed
pile in a bead-like
karst area. The constructing method comprises the following steps that S1, thedesign elevation of each
pile is optimized and determined through detailed exploration of one
pile with multiple holes; S2, a plurality of vertical steel pipes is evenly pre-embedded on each pile body along the pile circumference; S3, the bottom of each pile is subjected to core-taking and additional exploration by using steel
pipe passages, and whether soft
layers are at the bottom of each pileor not and the specific distribution of the soft
layers are determined combined with the detailed exploration; S4,
cutting,
broaching and cleaning of the soft
layers are completed in the force bearingrange of the bottoms of the piles; S5, the soft layers in the force bearing range of the bottoms of the piles are replaced; S6, orifice
slurry supplying is performed; and S7, orifice shut-off
pressure grouting is performed. By the thought and method that the continuous bearing layer is actively introduced and constructed at the bottoms of the piles in the
design process, the selection range of the elevation of the bearing layer of the pile ends is expanded, the design is effectively optimized, and the designed pile length is shortened; and through the integrated process such as high pressurecutting, cleaning and double fluid grouting, the continuous bearing layer is formed, and the potential
quality safety hazards of the socketed pile bottom are actively eliminated.