Patents
Literature
Hiro is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Hiro

130results about How to "Reduce time spent working at heights" patented technology

Power transmission tower reinforcing clamps, power transmission tower reinforcing device and power transmission tower reinforcing method

The invention discloses power transmission tower reinforcing clamps, a power transmission tower reinforcing device and a power transmission tower reinforcing method. Each power transmission tower reinforcing clamp comprises a main body and a matched part, wherein the main body comprises a clamping part and a connection part which are connected; the clamping part and the matched part are matched to clamp a power transmission tower main material; the joint of the clamping part and the matched part is located in the positions where the clamping part and the matched part extend through the two side edges of the power transmission tower main material. The power transmission tower reinforcing device comprises the multiple power transmission tower reinforcing clamps and a plurality of reinforcing parts. The reinforcing parts are fixed to the power transmission tower main material through the power transmission tower reinforcing clamps, meanwhile, every two adjacent reinforcing parts are in butt joint and are then connected with a shoe plank on a power transmission tower foot plate. The power transmission tower reinforcing method ensures the reinforcing effect of a power transmission tower through combination of finite element analysis and tests. The power transmission tower reinforcing clamps are simple to install, and the power transmission tower reinforcing device and the power transmission tower reinforcing method improve the strength of the power transmission tower.
Owner:CHINA ENERGY ENG GRP GUANGDONG ELECTRIC POWER DESIGN INST CO LTD

Construction method of superlong cable beam-free sections of cable-stayed bridge

The present invention relates to a construction method of superlong cable beam-free sections of a cable-stayed bridge. The first stage refers to the construction of five middle beam sections: the bracket+floating crane installation method is adopted, that is, the five cable beam-free sections in the middle of a tower area are sequentially hoisted up and placed on a lower beam bracket by using a floating crane, and tower beam temporary restraints are installed after the beams are connected into a whole. The second stage refers to the construction of two beam sections at the two ends: the platform+deck crane installation method is adopted, that is, the beam sections at each end are connected together on the backfield in advance and then stored on cofferdam top platforms on the both sides of a main tower, a deck crane above lifts and installs the beam sections, the lifting of the deck crane is conducted by using a midspan-and-then-sidespan asymmetry method, and the counterweight is increased or decreased in the construction process to decrease the unbalanced bending moment in the construction process. The construction method has unique advantages in terms of construction economy, construction cycle and construction safety, and the purpose of not applying floor steel pipe piles is realized.
Owner:ROAD & BRIDGE EAST CHINA ENG +1

Support-free mounting method of fabricated concrete frame building

The invention provides a support-free mounting method of a fabricated concrete frame building. The support-free mounting method comprises the following steps of modeling prefabricated parts and connecting tools by adopting BIM to obtain a mounting scheme of the prefabricated parts and the connecting tools, wherein the prefabricated parts comprise prefabricated columns, prefabricated main beams, prefabricated secondary beams and prefabricated laminated slabs, and the connecting tools comprise beam and column connecting joints, primary and secondary beam connecting joints and beam and plate connecting joints; installing the prefabricated columns, installing the beam and column connecting joints on the prefabricated columns, and placing the prefabricated main beams on the beam and column connecting joints; installing the main and secondary beam connecting joints on the prefabricated main beams and the prefabricated secondary beams, and connecting the prefabricated main beams with the prefabricated secondary beams through the main and secondary beam connecting joints; installing the beam and plate connecting joints on the prefabricated main beams and the prefabricated secondary beams,and placing the prefabricated laminated slabs on the beam and plate connecting joints; conducting cast-in-place construction; and dismounting the connecting tools. By the adoption of the method, a traditional scaffold installation system can be omitted, and the advantages of a fabricated building are brought into full play.
Owner:GUANGDONG JIAN YUAN CONSTR ASSEMBLY IND CO LTD +2

Integral installation device for transformer test bench

An integral installation device for a transformer test bench is used for integrally installing the transformer test bench and comprises a double-electric-pole horizontal correction mechanism, transformer test bench integral hanging support arms, hoisting transverse arms and a transverse arm adjustment support. The double-electric-pole horizontal correction mechanism is formed by no less than two horizontal correction units, wherein a V-shaped supporting block, a hydraulic jack, a supporting body and a bottom plate are arranged in each horizontal correction unit. The V-shaped supporting blocks are arranged in a bilaterally symmetrical mode and respectively positioned at the ends of the two hydraulic jacks. The spacing L1 of the central axis of the two V-shaped supporting block meets the distance requirement of the standard bench area rod root of the transformer test bench. The hydraulic jacks are fixed on the supporting bodies which are fixed at two ends of the bottom plates, and the bottom plates are arranged on the horizontal ground. By means of the integral installation device for the transformer test bench, time consumed by construction personnel working high above the ground is reduced to the largest extent, labor intensity of the construction personnel is reduced, working efficiency is improved, and the building construction of the 10kV transformer test bench is standardized and normalized.
Owner:STATE GRID CORP OF CHINA +2

Integrated hoisting method for corrugated steel web part

The invention discloses an integrated hoisting method for a corrugated steel web part. The method includes the following steps that a hanging basket is moved forward in place on the N-1th corrugated steel web section of a corrugated steel web PC box girder bridge, so that the bottom of the hanging basket is fixed to the N-1th corrugated steel web section, and the top of the hanging basket protrudes out of the front end of the N-1th corrugated steel web section; precast splicing of the Nth corrugated steel web section is completed in a factory, the Nth corrugated steel web section is composed of a plurality of longitudinal corrugated steel webs, and the corrugated steel webs are fixedly connected with transverse steel cross beams and temporary supporting and reinforcing devices; by means of a flat plate barge, the Nth corrugated steel web section is conveyed to the position under the design position; by means of a hoisting system located on the top of the hanging basket, the Nth corrugated steel web section is hoisted in place, and the Nth corrugated steel web section and the N-1th corrugated steel web section are connected. The integrated hoisting method has the advantages that the construction period is effectively shortened, construction quality is improved, and aloft work time is shortened.
Owner:SHANGHAI URBAN CONSTRUCTION MUNICIPAL ENGINEERING (GROUP) CO LTD

Triangular supporting bracket of suspended cast bridge block 0

The invention relates to engineering machinery, in particular to a triangular supporting bracket of a suspended cast bridge block 0. The triangular supporting bracket comprises at least one set of supporting frames, wherein the supporting frames comprise horizontal girders installed on bridge pier bodies and further comprise diagonal bracing beams, wherein the upper portions of the diagonal bracing beams are connected with the horizontal girders, the lower portions of the diagonal bracing beams are connected with reinforcing steel plates, the bottom faces of the reinforcing steel plates are connected with transverse beams, the lower portions of the transverse beams are connected with bolt rods, and the bolt rods are inserted into reserved holes in the bridge pier bodies. The fixing operation of the lower ends of the diagonal bracing beams can be completed only by inserting the bolt rods into the bolt rod reserved holes in the bridge pier bodies, the triangular supporting bracket is convenient to use, operation work types are few, cross operation and mutual interference are decreased, and labor intensity of workers is reduced. The triangular supporting bracket is low in installation technology difficulty, can be installed by adopting a common work type and does not need special workers, and manpower resource configuration is optimized. In conclusion, cost is effectively saved, efficiency is improved, and the triangular supporting bracket is safe and provides a guarantee.
Owner:福建第一公路工程集团有限公司

Construction method of metal curtain wall at bottom of high altitude steel structure

The invention provides a construction method of a metal curtain wall at the bottom of a high altitude steel structure. The construction method comprises the steps that a plurality of curtain wall mounting modules are assembled according to the outer contour of the steel structure; the gravity center positions of all the curtain wall mounting modules on the roof of a podium building or the top plate of a basement are determined, and hoisting equipment mounted on the positions corresponding to the gravity centers of all the curtain wall mounting modules on the steel structure; one of the curtainwall mounting modules is lifted to the preset height through the hoisting equipment; the curtain wall mounting modules are connected with the steel structure main body; the step 3 and the step 4 arerepeated, after mounting of other curtain wall mounting modules is sequentially completed, edge closing treatment is conducted, and namely mounting of the whole metal curtain wall can be completed. According to the construction method, the curtain wall mounting modules serve as hoisting units, the hoisting equipment is mounted on a mounting layer, the curtain wall mounting modules are fixedly connected with the steel structure main body after all the curtain wall mounting modules are integrally and sequentially hoisted and take place, the whole metal curtain wall is mounted, the mounting difficulty is greatly lowered, the construction speed is accelerated, and the construction period is shortened.
Owner:CHINA MCC20 GRP CORP

Removing method of lifting cover for hoisting

ActiveCN102583149AShorten demolition preparation timeReduce job preparation timeLoad-engaging elementsMarine engineeringFlange
The invention relates to a removing method of a lifting cover for hoisting. The removing method is characterized by comprising the following steps of: installing the lifting cover and an operating platform on equipment to be hoisted; connecting hoisting ropes, starting a main hoist to hoist the equipment to be hoisted to an equipment installing foundation in position; hoisting operators to the operating platform by using an auxiliary hoist, loosening double-head studs and nuts for fixing the lifting cover and equipment flanges, and then returning the operators to the ground by using the auxiliary hoist; lifting a hoisting hook of the main hoist, separating the operating platform and the lifting cover from a top flange of the equipment; rotating an arm rod of the main hoist, and falling the hoisting hook, till the operating platform and the lifting cover fall to the ground; and disassembling the operating platform and the lifting cover on the ground. The removing method has the advantages that by specially-designed matching of the operating platform and the lifting cover, the lifting cover and the operating platform can be quickly disassembled from the equipment after the hoisting is finished, and then the operating platform is separated from the lifting cover on the ground, so that the working efficiency and the hoisting safety are greatly improved, and meanwhile the hoisting construction cost is also reduced.
Owner:CHINA PETROLEUM & CHEM CORP +2

Laser measurement correction system and method for external wall of high-rise building

ActiveCN107843243ASolve the difficulty of measurement controlSolve the accuracy problemReference line/planes/sectorsFixed frameComputer module
The invention discloses a laser measurement correction system and method for an external wall of a high-rise building. The system comprises a control unit, a standard measurement correction unit and aplurality of measurement correction units, wherein the standard measurement correction unit and the measurement correction units are mounted on the same plane and are mutually networked to form a grid structure; the structure of the standard measurement correction unit is the same as that of each measurement correction unit; each unit comprises a cross-shaped structure main body, an adjusting rodand a fixed frame; each cross-shaped structure main body comprises two laser emitting devices, two laser receiving devices, a signal sending module and a horizontal pointer, wherein the two laser emitting devices are arranged at positions of two adjacent cross-shaped tips on the cross-shaped structure main body respectively, and the two laser receiving devices are arranged at positions of the other two adjacent cross-shaped tips on the cross-shaped structure main body respectively. The laser measurement correction system disclosed by the invention has the advantages that the measurement precision is high, the labor cost of construction can be effectively reduced, the system can be circularly utilized for a plurality of times and energy saving and environment protection are realized.
Owner:CHINA FIRST METALLURGICAL GROUP

Novel steel-concrete beam-column joint construction structure and comprehensive construction method

PendingCN107489277AIncrease profitSolve the deficiencies of deepeningBuilding material handlingConcrete beamsArchitectural engineering
The invention provides a novel steel-concrete beam-column joint construction structure and a comprehensive construction method. A joint three-dimensional model is established by utilizing a BIM technology before main body structure construction, connecting joints of concrete beams and steel reinforced columns are deepened, rebar putting plate integrated processing is conducted by utilizing BIM data, the BIM technology is utilized to simulate joint construction before on-site construction, and an optimal scheme is determined; the steel reinforced columns are transported to a construction site for being installed, column longitudinal bars are fixed to the outer sides of the steel reinforced columns through rebar putting plates in the vertical direction, and beam longitudinal bars and torsional bars are fixed in the transverse direction; and concrete pouring is conducted. Joint deepening, three-dimensional expressing, construction simulating are conducted by utilizing the BIM technology, so that conciseness and efficiency are achieved. The rebar putting plates are precisely welded to the steel reinforced columns in advance, on-site construction is extremely convenient, and the construction period is shortened. The invention belongs to the technical field of building construction.
Owner:CCFED THE FIRST CONSTR & ENG +1

Prefabricated valve set for four-pipe fan coiler

InactiveCN108825839AImprove the quality of engineering constructionThe quality and appearance are neat and beautifulPipe supportsFlanged jointsEngineeringVALVE PORT
The invention provides a prefabricated valve set for a four-pipe fan coiler. The prefabricated valve set comprises a support, an electric two-way valve, a first ball valve, a second ball valve and a filter. The support comprises a steel channel, first supporting plates and second supporting plates. Multiple first supporting plates are fixedly connected to the outer side of the first side wall of the steel channel. Multiple second supporting plates are fixedly connected to the outer side of the second side wall of the steel channel. The first side wall and the second side wall are parallel. Thefirst end of the electric two-way valve is connected with the first end of the first ball valve through a first pipe section. The first end of the filter is connected with the first end of the secondball valve through a second pipe section. The first pipe section penetrates through holes in the first supporting plates, and the second pipe section penetrates through holes in the second supportingplates. According to the prefabricated valve set, the project construction quality is improved greatly, the prefabricated valve set has integrality and compactness, and is easy to install, and unnecessary potential safety hazards of high-altitude operation are avoided.
Owner:CHINA CONSTR THIRD ENG BUREAU INSTALLATION ENG CO LTD +1

Prefabricated corner wall and construction method

The invention discloses a prefabricated corner wall. The prefabricated corner wall is provided with a first wallboard and a second wallboard which are connected vertically, and the inner sides of theconnection ends of the first wallboard and the second wallboard are both connected with the side face of a first vertical square pipe; the inner side of the first wallboard is connected with the sideface of a second vertical square pipe, and the inner side of the second wallboard is connected with the side face of a third square pipe; the horizontal distance between the second vertical square pipe and the end of the first wallboard, and the horizontal distance between the third vertical square pipe and the end of the second wallboard are 45-70 mm separately; a plurality of transverse square pipes are arranged between the first vertical square pipe and the second vertical square pipe as well as between the first vertical square pipe and the third vertical square pipe at intervals; the inner sides of the first wallboard and the second wallboard are fixedly provided with transverse steel belts connected with the transverse square pipe, the first vertical square pipe, the second verticalsquare pipe and the third vertical square pipe; and the two ends of each transverse steel belt are each provided with an extension segment, and the inner sides of the first wallboard and the second wallboard are coated with first insulating layers with the thickness of 35-40 mm.
Owner:ZHONGKE QIYE (DALIAN) TECH CO LTD

Segmented hoisting construction method for steel grid frame structure

The invention discloses a segmented hoisting construction method for a steel grid frame structure. A steel grid frame structure to be hoisted comprises a lower layer grid frame and an upper layer gridframe, the lower layer grid frame and the upper layer grid frame are each formed by assembling four chord balls and chord members, and the lower layer grid frame and the upper layer grid frame are connected through web members. The segmented hoisting construction method comprises the following steps: 1, construction preparation is conducted; 2, the steel grid frame structure is segmented; 3, thesteel grid frame segments are assembled; 4, a temporary support for hoisting the steel grid frame segments is mounted; and 5, the steel grid frame structure is segmentally hoisted. The construction operation is convenient and fast, the steel grid frame structure is divided into the multiple steel grid frame segments, the method that the steel grid frame segments are assembled on the ground, and then the assembled steel grid frame segments are hoisted one by one is adopted, thus the assembling quality and the assembling efficiency of the steel grid frame segments can be effectively improved; and the temporary support is adopted for temporary supporting in the hoisting process of the steel grid frame segments, the installation precision of the steel grid frame segments can be effectively guaranteed, the aerial work time during hoisting of the steel grid frame structure is shortened, and the safety risk is small.
Owner:中铁二十局集团市政工程有限公司

Portable 5G base station antenna and base station

The invention relates to a portable 5G base station antenna and a base station. The portable 5G base station antenna comprises a first mounting rack, a holding clamp capable of fixing the first mounting rack on a holding pole, and an antenna body mounted on the first mounting rack; the first mounting rack comprises two first clamping plates which are arranged at intervals in a vertical direction, outer rods arranged on the outer rings of the first clamping plates, middle rods connected between the first clamping plates and the outer rods and a plurality of connecting plates for connecting the two first clamping plates, and the first mounting rack can be locked and prop against the holding pole through a locking piece after being matched with the holding clamp; and the antenna body is installed on the outer rods through angle positioning structures, and the side surface of the antenna body is provided with an angle indicator for naked eyes to see degrees. According to the portable 5G base station antenna and the base station of the invention, manual carrying and manual installation can be conveniently carried out, and the installation of an installation bracket can be carried out by a lifting rope for several times, so that the installation bracket can be suitable for various remote installation places with inconvenient traffic.
Owner:北京鑫昇科技有限公司

Cable saddle rigidization structure and integral position-fixing and mounting method thereof

The invention relates to a cable saddle rigidization structure and an integral position-fixing and mounting method thereof. The cable saddle rigidization structure comprises a section steel frame bodyand multi-layer cable saddles mounted on the section steel frame body, wherein the position fixing of the multi-layer cable saddles relative to each other is achieved through relative coordinates; relative space angles of the multi-layer cable saddles are ensured to be in accordance with relative space angles of cable saddles in cable bent tower segments; the section steel frame body comprises frame body vertical rods corresponding to embedded parts in the cable bent tower segments in position, position-fixing horizontal rods transversely connected to the frame body vertical rods, and frame body horizontal rods longitudinally connected to the frame body vertical rods; the cable saddles are placed on the position-fixing horizontal rods; and the positions of the cable saddles are fixed through position-limiting section steel. The multi-layer cable saddles are controlled through the relative coordinates during rigidization, so that the relative positions of the multi-layer cable saddlesare guaranteed. The multi-layer cable saddles are integrally hoisted to the tower after rigidization and then controlled through absolute coordinates. The position fixing is fast, and the position fixing precision is high. In addition, position fixing performed aloft is not needed, and the construction of a cable bent tower is not affected, so that the overall construction progress is accelerated.
Owner:ZHEJIANG COMM CONSTR GRP CO LTD +1

Fabricated bridge substructure and construction method thereof

The invention discloses a fabricated bridge substructure which comprises a foundation structure, a prefabricated bent cap and a quasi-prefabricated pier column unit, and foundation reserved vertical ribs are arranged at the top of the foundation structure; cover beam reserved vertical ribs are arranged on the lower side of the prefabricated bent cap. At least one sprue gate vertically penetrating through the prefabricated bent cap is arranged in the area covered by the reserved vertical ribs of the bent cap; a standard prefabricated pier column unit is a hollow cylinder with openings in the upper portion and the lower portion and penetrates through the foundation reserved vertical ribs to be vertically inserted into the top of the foundation structure; the prefabricated bent cap is in lap joint with the top of the standard prefabricated pier column unit and extends into the hollow area of the standard prefabricated pier column unit through the cover beam reserved vertical ribs to be connected in an inserted mode. Expansion concrete is cast in situ in the sprue gate and the hollow area of the standard prefabricated pier column unit. The construction quality can be controlled in a cast-in-place and prefabricating combined mode, investment of formworks is omitted, the weight is low, installation is convenient and rapid, the aerial work time can be effectively shortened, the construction efficiency is improved, and the construction period is shortened.
Owner:SICHUAN JIAOTOU CONSTR ENG CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products