The invention belongs to the field of constructional
engineering construction, and particularly relates to a
basement roof settlement post-cast strip pre-sealing construction method. The
supporting system of the structural top plates on the two sides of the post-cast strip comprises a
scaffold formwork
supporting system and a supporting column
supporting system. After structural top plate concrete pouring reaches the strength, a
scaffold formwork supporting
system is dismantled, a post-cast strip is fully laid through supporting
steel plates, grouting steel pipes are arranged on the
middle line of the post-cast strip at intervals, sealing plates are fixed to top
pipe openings of the grouting steel pipes in a
spot welding mode, and waterproof treatment is conducted on the post-cast strip area; after construction of the main body structure is completed, a formwork supporting
system of the post-cast strip part is erected, the sealing plate is removed, and post-cast strip grouting is conducted through the grouting steel
pipe; and after the concrete strength of the post-cast strip meets the design requirement, the supporting column supporting systems on the two sides of the post-cast strip are dismantled. According to the pre-sealing construction method for the
basement roof settlement post-cast strip, the construction cost can be reduced, the construction period can be shortened, and meanwhile the safety and stability of structures on the two sides of the post-cast strip are met.