The invention relates to the technical field of
thermal insulation building block preparation, in particular to a one-time stacking burning
thermal insulation building block preparation mechanism and a preparation process, the one-time stacking burning
thermal insulation building block preparation mechanism comprises a
kiln and a central roller conveying line, the conveying line of the central roller conveying line passes through the
kiln in the front-back direction and is used for heating,
sintering and conveying thermal insulation building blocks, and the central roller conveying line comprises a left
side branch line and a right
side branch line; the left
side branch line comprises a row of left conveying rollers which are arranged on the left side furnace wall of the
kiln in a penetrating mode and distributed front and back at intervals, the right side
branch line comprises a row of right conveying rollers which are arranged on the right side furnace wall of the kiln in a penetrating mode and distributed front and back at intervals, and the left conveying rollers and the right conveying rollers are arranged left and right at intervals and form
sintering heat circulation intervals at intervals; a top fuel
nozzle is arranged at the top of the kiln, a bottom fuel
nozzle is arranged at the bottom of the kiln, a heat preservation building block stacking and bearing
moving frame capable of being placed at the right end of the left conveying roller and the left end of the right conveying roller is further arranged between the left side
branch line and the right side
branch line, the heat preservation building block stacking and bearing
moving frame can be ventilated vertically, and the
sintering effect is better.