The invention relates to a construction method for enabling a cable to pass through a barrier. The construction method for enabling the cable to pass through the barrier sequentially includes following steps: firstly, confirming a
pipe hole path so as to obtain the total length and the specification of a cable sleeve, prefabricating the cable sleeve by sections, threading a steel wire lead
rope through the cable sleeve in advance, clearing the inner wall of the cable sleeve section by section, and performing anticorrosion and mouth repairing on the cable sleeve after a qualified pressure test on the cable sleeve is completed; then, performing a
simulation experiment, obtaining a slide
friction coefficient of the cable sleeve, figuring out the maximum slide traction resistance, judging whether the maximum slide traction resistance is larger than permissive
pull force of the cable, and if yes, installing
idler wheel hoops for a second experiment so as to obtain a rolling
friction coefficient of the cable sleeve, figuring out the maximum rolling traction resistance during the cable passing process, and confirming specifications of traction facilities of a main steel
wire rope and the like; finally, drilling
pipe holes, enabling the cable to pass through the cable sleeve, using a winching to tow the cable, using an
excavator to assist in cable feeding, feeding the cable in the cable sleeve for a section after installing each batch of the
idler wheel hoops until the whole cable completely passes through the cable sleeve, and performing a performance test on the cable which passes through the cable sleeve after two end mouths of the cable sleeve are blocked. The construction method for enabling the cable to pass through the barrier can substantially reduce passing resistance of the cable, and is safe and reliable.