The invention relates to the field of railway construction, and provides a railway
contact network bearing wire replacement construction method which comprises the following steps: S1, preparing construction before wire replacement; s11, breaking and dismantling the existing crimping type electric connecting wire clamp, and replacing the existing crimping type electric connecting wire clamp with a bolt type electric connecting wire clamp; s12, the old elastic crane is temporarily dismantled; s13, parameters of the existing anchor section and elastic hoisting tension are comprehensively measured; s14, the anchor section parameters are divided into 30 sections of anchor section supporting column parameters, and the 30 sections of anchor section supporting columns are anchor section supporting columns from the first anchor section supporting column to the third anchor section supporting column; s15, operation vehicle
marshalling:
marshalling constant tension vehicles according to construction requirements; s16, making a working vehicle operation plan, and moving the working vehicle to a specified anchor section support column according to a No.30 anchor section support column; s2, line changing construction is carried out; S21, a carrier cable is replaced; s22, replacing a
contact line; s3, fine adjustment construction; s31, the
catenary is finely adjusted; and S4, performing dynamic inspection to recover the normal speed. The method has the effects of formulating the path of the anchor section strut and the operation vehicle and ensuring the operation stability.