Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

44results about How to "Improve the level of construction technology" patented technology

Plateau mountain foundation pit excavation construction device

A plateau mountain foundation pit excavation construction device comprises a braced frame. The braced frame is provided with a walking supporting mechanism and a supporting frame. The supporting frame is perpendicularly provided with a sliding way rack. A lifting support is arranged at the upper end of the sliding way rack. A sliding way is perpendicularly arranged in the sliding way rack. The sliding way rack is provided with a double-stepping transmission mechanism. A rotary driving device connected with the double-stepping transmission mechanism is arranged in the sliding way in a sliding mode. The power output end of the rotary driving device is connected with a drilling device. An excavation mechanism and a soil lifting mechanism are arranged at the lower end of the driving device. According to the plateau mountain foundation pit excavation construction device, design is reasonable, the automation degree is high, manual labor intensity is fully relieved, the safety degree and the reliability degree are high, and work efficiency of excavation of pile holes is improved; according to a line project pile hole foundation excavation mode, the research on foundation fit excavation mechanical operation machines and tools for a plateau mountain transmission line special foundation is conducted, the device is made to meet the technical requirements of a line construction excavation pile foundation, and the construction mechanization degree and construction efficiency of an alternating current transmission line project are improved.
Owner:STATE GRID CORP OF CHINA +4

Drilling, excavating and soil lifting device of plateau mountain land foundation pit excavation construction equipment

The invention relates to a drilling, excavating and soil lifting device of plateau mountain land foundation pit excavation construction equipment. The drilling, excavating and soil lifting device comprises a support framework, wherein a support frame is arranged on the support framework; two slideway frames are vertically arranged on the support frame; an ascending and descending bracket is arranged between the upper ends of the two slideway frames; a slideway is vertically arranged in each slideway frame; a doubling transmission mechanism is arranged on the slideway frames; a rotation driving device connected with the doubling transmission mechanism is glidingly arranged in the slideways; the power output end of the rotation driving device is connected with a drilling mechanism; and the lower end of the drilling mechanism is provided with an excavating mechanism and a soil lifting mechanism. The drilling, excavating and soil lifting device has the advantages that the design is reasonable; the automation degree is high; the work intensity of workers is sufficiently reduced; the safety degree and the reliability degree are high; the work efficiency of pile hole digging is improved; according to a line project pile hole digging foundation type, the study on plateau mountain land electric transmission line special basic foundation pit mechanization operation machine tools is developed, so that the technical requirements of line construction hole pile foundation digging are met; and the construction mechanization degree and the construction efficiency of an alternating current transmission line project are improved.
Owner:STATE GRID CORP OF CHINA +3

Simultaneous construction type wide-flanged guyed traveler

The invention discloses a simultaneous construction type wide-flanged guyed traveler, which comprises a front transverse beam, a middle transverse beam and a rear transverse beam, a main longitudinal girder and a secondary longitudinal girder are sequentially connected among the front transverse beam, the middle transverse beam and the rear transverse beam, the two ends of the middle transverse beam and the rear transverse beam respectively extend to the outer side of the main longitudinal girder so as to form a wide-flanged board casting platform, the two ends of the middle transverse beam are respectively fixedly connected with a C-shaped hook, the middle transverse beam and the rear transverse beam are respectively fixedly connected with a square shear-resisting column, and the shear-resisting column extends to a positioning hole arranged at the joint of an inclined web plate of a bridge body and a bottom plate.A thrust system of the invention is simple in construction, clear in stress and strong in maneuverability, can give full play to the local bearing capacity of high-strength concretes, and completely meet the construction needs; and because the construction period of each cantilever casting section is shortened by 2 to 3 days, thereby improving the construction speed and shortening the construction period of each cantilever casting section.
Owner:THE SECOND CONSTR OF CTCE GROUP

Digging and soil lifting device for plateau mountain foundation pit digging construction equipment

The invention provides a digging and soil lifting device for plateau mountain foundation pit digging construction equipment. The digging and soil lifting device comprises a support framework, a guide drill rod, a digging mechanism and a soil lifting mechanism, wherein a support frame is arranged on the support framework; two slide passage frames are vertically arranged on the support frame; the upper ends of the two slide passage frames are provided with an ascending and descending support frame; and the outer surface of the guide drill rod is symmetrically provided with two guide rails in the axial direction. The digging and soil lifting device has the advantages that the design is reasonable; the automation degree is high; the work intensity of workers is sufficiently reduced; the safety and reliability degree is high; the work efficiency for digging pile holes is improved; according to the basic line engineering pile hole digging mode, the study on a special basic foundation pit digging mechanical operation machine tool of plateau mountain power transmission lines is developed, so that the technical requirements of line construction hole pile foundation digging can be met; the construction efficiency and the engineering construction mechanization degree of alternating current power transmission lines are improved; and the hole pile digging foundation construction technical level is promoted to be further improved.
Owner:STATE GRID CORP OF CHINA +3

Building shading cast-in-place concrete lattice wall and construction method thereof

The invention discloses a building shading cast-in-place concrete lattice wall and a construction method of the building shading cast-in-place concrete lattice wall. The building shading cast-in-place concrete lattice wall comprises a concrete cast lattice wall body and steel reinforcements pre-embedded in the wall body. The construction method of the building shading cast-in-place concrete lattice wall comprises the following steps: 1), manufacturing and mounting a template, wherein the template comprises an outer side template and an inner side template spliced with each other, and a plurality of core templates clamped and fixed between the outer side template and the inner side template; wherein each core template comprises a keel and an inclined supporting structure in the keel; 2), manufacturing the steel reinforcements layer by layer according to the cast layer level of the concrete of the lattice wall; 3), constructing the concrete layer by layer; and 4), disassembling the templates and maintaining the concrete. According to the building shading cast-in-place concrete lattice wall and the construction method, the concrete surface of the building shading cast-in-place concrete lattice wall is not necessarily decorated, and the natural performance and artful texture of the concrete are shown, in this way, the purposes of strengthening the artistic effect, saving the construction cost and shortening the construction period are fulfilled.
Owner:ZHEJIANG HAITIAN CONSTR GROUP

Bailey beam support construction method based on variable section capping beam and support building system

The embodiment of the invention discloses a bailey beam support construction method based on a variable section capping beam and a support building system. The bailey beam support construction methodbased on the variable section capping beam comprises the steps of step S1, construction of a support foundation; step S2, mounting of steel uprights; step S3, erection of multiple groups of bailey beam groups; step S4, mounting of upper I-shaped steel; step S5, laying of square timber and a bottom die; and step S6, construction of the variable section capping beam. According to the bailey beam support construction method based on the variable section capping beam and the support building system, as the support building system is a support system adopting the steel uprights+bailey beams+I-shaped steels, the pouring quality and safety of a diagonal bracing system at the variable section part can be guaranteed, the construction progress is accelerated, the construction period is shortened, the cost of the support construction system is also reduced, and the amount of labor used is reduced; with the continuous advancement of construction technology, it is particularly important to pay attention to the construction efficiency and quality; and the adoption of a bailey support system is undoubtedly more time-saving, economic, scientific and feasible.
Owner:SINOHYRDO ENG BUREAU 3 CO LTD

Offshore bridge erecting machine and construction method thereof

The invention discloses an offshore bridge girder erection machine and a construction method thereof, and relates to the technical field of offshore platform construction. The construction method of the offshore bridge girder erection machine comprises the steps of bridge girder erection machine assembling, bridge girder erection machine testing, bridge girder erection machine in-place placing, prefabricated part installing and bridge girder erection machine moving. According to the construction method of the offshore bridge girder erection machine, improvement is performed on the basis of bridge girder erection machines for highways and railways, a front supporting leg structure of the bridge girder erection machine is transformed, and is suitable for requirements for different steel pipepile intervals and loads; meanwhile, the transition joints are arranged on the steel pipe piles of the front supporting legs, and the function of front-back and left-right adjustment is achieved so as to adapt to the horizontal construction deviation of the steel pipe piles or the concrete piles on the lower portion; the middle supporting leg structure is improved, so that the middle supporting leg structure can adapt to the characteristic that steel bars on pier caps at the tops of steel pipe piles are complex, water operation is changed into road construction finally, influences of adversefactors such as surges and tides are reduced, meanwhile, the construction progress is accelerated, the installation quality is improved, and the construction cost is reduced.
Owner:SINOHYDRO BUREAU 5

Underground gas storage and site selection and transformation method thereof

The invention discloses an underground gas storage and a site selection and transformation method for reconstructing the underground gas storage by using a waste mine hole, high-pressure gas is sealed and stored by fully utilizing good sealing performance, low permeability and underground water pressure of a natural stratum, and the construction cost of sealing measures of the underground gas storage can be greatly reduced; meanwhile, underground waste spaces such as the goaf of the waste mine cave and various waste caverns are utilized, and the utilization efficiency of the underground waste spaces is greatly improved; in addition, the abandoned mine cave roof determined according to the site selection step has the advantages of being good in deformation resistance, high in strength and the like, and therefore large-scale reinforcement treatment does not need to be conducted on an original abandoned goaf and a roadway of the original abandoned goaf, and the construction cost of project reconstruction is greatly reduced. The anti-seepage structure is simple, the engineering construction process is simple, the construction technical difficulty is small, and the construction technical level of reconstructing a large-scale underground gas storage by using the abandoned mine can be further improved.
Owner:CHANGSHA UNIVERSITY OF SCIENCE AND TECHNOLOGY

High-rise building integrated construction method and high-rise building integrated construction platform

The invention relates to the technical field of high-rise building integrated construction, in particular to a high-rise building integrated construction method which comprises the following steps that S1, a vertical formwork in a formwork system is driven by a lifting assembly on a top steel structure to descend; s2, the vertical mold plate is subjected to mold closing under the operation of an automatic mold opening and closing device; s3, the vertical formwork falls to the N-layer ground; s4, the vertical formwork is separated from a lifting assembly on the top steel structure; and S5, the concrete distribution robot is lifted upwards by the height of one floor, and the concrete distribution robot climbs from the interior of the elevator shaft in a hydraulic self-climbing mode. The purposes of reducing the manual operation workload and improving the industrialization level of building construction are achieved, the construction method is advanced, reasonable and efficient, the construction cost is effectively reduced, the construction period is shortened, meanwhile, orderly proceeding of all procedures is improved, and the construction progress is improved on the premise that the project quality is guaranteed.
Owner:安徽同湃特机器人科技有限公司

Opening-closing type salvaging device for drilled pile drill bits

The invention discloses an opening-closing type salvaging device for dilled pipe drill bits. A housing is a thin-wall cylindrical tapered barrel; a limiting rod passes through from a housing; an upper limiting bolt and a lower limiting bolt are welded on the limiting rod; four rod outlet windows are vertically formed in the side wall of the housing; two connecting rods are separately welded horizontally in two vertical inside centers of the rod outlet windows; guide slide sleeves are hinged between the two connecting rods in the rod outlet windows by taking the side wall as the center; a limiting slide sleeve is arranged between the upper limiting bolt and the lower limiting bolt of the limiting rod; movable rods are connected to the limiting slide sleeve in a manner of enabling a fixing rod to pass through a horizontal hole; the four movable rods on the limiting slide sleeve separately pass through four guide slide sleeves in corresponding directions to get out from the housing. The limiting slide sleeve upwards slides along the limiting rod, the movable rods are opened and the limiting slide sleeve downwards slides along the limiting rod, so that the movable rods are closed. The device realizes multi-angle all-around salvaging work for multiple drill bits in drilled holes and karst caves, and has great significance on improving the technical level of pile foundation construction.
Owner:惠州市公路管理局 +1

Mounting construction method for joining truss of pipe truss structure system

The invention provides a mounting construction method for a joining truss of a pipe truss structure system, and belongs to the technical field of pipe truss mounting construction. Through the form ofarranging a connecting sleeve at the end of a reinforcing rod piece, the length of the reinforcing rod piece is adjusted through extending and retracting of the connecting sleeve, and thus the problemof interference of the reinforcing rod piece and a main rod is solved; an intersecting opening is formed in one end of the connecting sleeve to be in welded connection with the main rod, the other end of the connecting sleeve and the reinforcing rod piece are subjected to girth welding, four plug welding holes are symmetrically formed in the connecting sleeve, and the plug welding holes and the reinforcing rod piece are subjected to plug welding to form welding seams. The mounting construction method has the advantages that the problem of intersecting opening interference of reinforcing rod piece mounting in a limited space is solved in the form of the fabricated connecting sleeve, and the butting quality of the reinforcing rod piece and the truss main rod is effectively improved; and inpipe truss mounting construction, the construction quality is good, the efficiency is high, economic benefits are obvious, the construction technical level of a pipe truss structure is increased, anddevelopment of the steel structure industry is promoted.
Owner:BEIJING SHOUGANG CONSTR GROUP

A simulation training system and method for UHV steel pipe tower

The invention discloses a system and method for extra-high-voltage steel tube tower simulating training. The system comprises a data layer, a central processing unit, an application layer and multiple distributed operating terminals, wherein the data layer, the central processing unit, the application layer and the distributed operating terminals are sequentially connected. The data layer comprises a simulation database, a test question database and a simulation operation database, wherein the simulation database is used for providing three-dimensional models and relevant data information of various devices for extra-high-voltage steel tube tower simulation and the test question database and the simulation operation database are used for student examinations. The application layer comprises a design module, a machining module, a construction module, a test question examination module and a simulation examination module. The system and method have the advantages that three-dimensional display and virtual simulation visual display of invisible parts and steel tube tower engineering application key technology in the processes of design, machining and construction of an extra-high-voltage steel tube tower are achieved, imagination and visualization training is achieved, trainees can more deeply understand and master the theory, and training time is shortened.
Owner:STATE GRID CORP OF CHINA +1

Guide limiting block for pipe shoe and installation method of guide limiting block

The invention discloses a guide limiting block for a pipe shoe and an installation method of the guide limiting block. The contour of the cross section of the guide limiting block is in a trunk shape, and the guide limiting block comprises a connecting edge, an inwards-concave section, a guide edge, a limiting edge and an outer contour edge which are connected end to end in the clockwise direction; the connecting edge, the inwards-concave section, the guide edge, the limiting edge and the outer contour edge extend in the thickness direction to form a connecting face, an inwards-concave face, a guide face, a limiting face and an outer contour face respectively; the guide limiting block is of a trunk-shaped structure, the connecting face is used for fixing, the inwards-concave face enlarges the gap between the guide limiting block and a pipe shoe bottom plate, welding and coating are facilitated; the guide face and the limiting face are arranged to limit the movement direction of the pipe shoe bottom plate and a pipeline, the guide and limiting effects are achieved, installation is convenient, and the construction procedure is optimized; and by applying the guide limiting block, the problem of corrosion prevention dead corners of the guide limiting block of a pipe shoe of a process pipeline of an offshore oil platform is solved, potential engineering quality hazards can be effectively avoided, and the effects of reducing economic cost and facilitating installation are achieved.
Owner:OFFSHORE OIL ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products