The invention provides a main net rack reconstruction and load
recovery implementation method based on a hydro-thermal power
generating unit, and relates to the technical field of power systems, and the method comprises the steps: obtaining key parameters (
voltage grade, structure, unit self-starting capability and the like) of a
power grid; constructing an electromagnetic transient
simulation model based on the information sorting unit capacity and the
line length; performing
overvoltage, unit paralleling and net rack reconstruction
simulation through the model; further establishing a
frequency response model, and simulating load
recovery; and finally, according to a
simulation result and actual scheduling data, a main net rack reconstruction and load
recovery scheme is formulated and deployed to a
power grid scheduling system. According to the method,
blindness of a
power grid dispatcher during power grid main grid structure reconstruction and load recovery in the power grid
black start process is overcome, and the problem that the dispatcher makes a decision difficultly in the
black start process is solved.