Patents
Literature
Patsnap Copilot is an intelligent assistant for R&D personnel, combined with Patent DNA, to facilitate innovative research.
Patsnap Copilot

279results about How to "Speed ​​up the construction period" patented technology

Construction method and structure for mounting reverse-construction steel pipe column in rotary drilled pile hole

ActiveCN104141301ALow costSolve long-term problemsBulkheads/pilesSocial benefitsReinforced concrete
The invention discloses a construction method and structure for mounting a reverse-construction steel pipe column in a rotary drilled pile hole. The construction method comprises the steps as follows: 1, drilling the pile hole; 2, mounting a reinforced concrete bearing platform; 3, hoisting a pile foundation reinforcement cage; 4, hoisting the steel pipe column; 5, mounting a concrete pouring platform; 6, cleaning the pile hole; 7, adjusting the elevation, the center position and the perpendicularity of the steel pipe column; 8, completing pouring of concrete in a pile foundation and the steel pipe column. The method is simple and practical, the construction period can be shortened, the project cost can be reduced, and the problem that the construction period is longer due to the fact that the pile foundation and the steel pipe column are constructed separately is solved. By the aid of the construction method and structure, the construction period is shortened while the project quality is guaranteed. The construction method and structure have the good social benefit and the good economic benefit. According to the construction method and structure, the high-efficiency construction requirement is met, the construction cost is saved, the project cost is reduced, the problem of continuous construction of rotary drilling and the steel pipe column in basement reverse construction is effectively solved, and the construction method and structure have the wide practicability and the popularization performance.
Owner:CHINA CONSTR FOURTH ENG DIV

Prefabricated, assembled and integrated type special-shaped column structure and jointing construction method thereof

The invention discloses a prefabricated, assembled and integrated type special-shaped column structure and a jointing construction method of the column structure. The prefabricated, assembled and integrated type special-shaped column structure comprises a prefabricated upper column, a prefabricated lower column and a prefabricated laminated beam, wherein the prefabricated upper column and the prefabricated lower column are respectively provided with channel steel in an embedding manner, reserved bolt holes are formed in each channel steel, the adjacent prefabricated upper column and prefabricated lower column are connected through the channel steel by bolts to form an upper and lower through special-shaped column provided with a cast-in-place area, and reinforcing hoops are arranged in the cast-in-place area; the prefabricated laminated beam is anchored in the abnormal column through a longitudinal rib of the prefabricated laminated beam; cast-in-place concrete is injected in the cast-in-place areas of the adjacent two prefabricated upper column and prefabricated lower column and a part, not pouring the concrete, of the prefabricated laminated beam, so as to form a beam and column combined whole body. According to the prefabricated, assembled and integrated type special-shaped column structure and the jointing construction method of the column structure, which are disclosed by the invention, the problems that the vibration of concrete in joint core area of the special-shaped column is not dense and is difficult can be remarkably modified, so that the vibration resistance of joints can be improved; furthermore, the construction speed further can be increased, the construction period is shortened, and the development of building industrialization is facilitated.
Owner:NANJING TECH UNIV +1

Construction method of shallow-buried subsurface-excavated cross-shaped cross-strut tunnel

The invention discloses a construction method of a shallow-buried subsurface-excavated cross-shaped cross-strut tunnel. The method includes the following steps of conducting construction preparation, conducting measurement and pay-off on a tunnel advanced support and the tunnel contour line according to construction design requirements, conducting advanced geological forecasting through the geophysical prospecting advanced geological forecasting and drilling advanced geological forecasting combined mode, conducting advanced pipe shed grouting and advanced curtain grouting, checking the grouting effect, entering the next procedure if the grouting effect meets the construction requirement, conducting advanced pipe shed and advanced curtain grouting again if the grouting effect does not meet the construction requirement, conducting excavation support construction on construction areas on by one from top to bottom and from left to right, conducting primary support and temporary support sealing and conducting monitoring and measuring after the primary tunnel transverse end face construction is completed, repeatedly executing the steps for the next circulation of construction if the design requirement is met, conducting support strengthening if the design requirement is not met, and regulating excavation parameters to conduct excavation support construction again till the design requirement is met.
Owner:ZHONGJIAN SUIDAO CONSTR CO LTD

Device and method for vertically transporting earthwork by reverse construction method

The invention relates to a device and a method for vertically transporting earthwork by a reverse construction method, which belong to the field of civil construction. In the device, segmental belt-type conveyor belts are adopted as earthwork transporting tools in a deep foundation pit; the conveyor belts pass through reserved holes of floor slabs on each floor; and the earthwork is transported to a dump truck obliquely from the bottom to the top by the conveyor belts. The device is formed by connecting independently segmented and obliquely arranged belt-type conveyor belts end to end; and each floor is provided with at least one conveyor belt which consists of an electric motor, a conveyor belt rack, an unloading tank, a scraping plate, a roller wheel, a roller wheel shaft bracket, a belt, a feeding funnel and an emergency brake device. The device and the method for vertically transporting the earthwork by the reverse construction method can effectively increase the earth volume in single vertical transport, effectively improve excavation efficiency, reduce excavation machines, reduce excavation cost, and simultaneously, reduce the influence of the construction of underground excavation on the simultaneous construction of an upper structure to the minimum.
Owner:CHINA CONSTR FIRST BUILDING GRP CORP LTD +2

Steel pipe-batten plate combined building column and construction technology thereof

The invention provides a steel pipe-batten plate combined building column and a construction technology thereof. The steel pipe-batten plate combined building column comprises a column skeleton and formworks detachably mounted outside the column skeleton, wherein the column skeleton comprises square steel pipes arranged at corners of the column skeleton and batten plates arranged between adjacent square steel pipes; the batten plates are arranged in the vertical directions of the square steel pipes according to certain intervals. The square steel pipes and the batten plates are combined to form the column skeleton, the steel pipe is arranged at each corner of the whole column skeleton, the formworks are arranged among the steel pipes, and then concrete is cast in place to form the steel-concrete combined column; the steel pipes are arranged at the corners of the column skeleton, while only batten plates are arranged at the middle positions of the column skeleton, so that when a beam is connected with an independent column, steel bars can freely extend into the column body and thus a fighting phenomenon of steel bars in the conventional reinforced concrete column is avoided; after the concrete is poured, a whole is formed, so that the rigidity in a node area is better.
Owner:SHANGHAI OPEN STEEL JOIST

Combined-type composite foundation with controllable rigidity piles, drainage materials and reinforced cushion

Disclosed is a combined-type composite foundation with controllable rigidity piles, drainage materials and a reinforced cushion. The reinforced cushion is laid on the surface of a soft soil foundation. The vertical drainage materials and the rigidity piles with caps are arranged in the foundation. Grouting tubes are installed between pile tops and the pile caps to form a controllable supporting system. When grouting is not conducted on the grouting tubes, drainage consolidation is conducted through the soft soil foundation under the effect of an upper load so as to improve the bearing capacity. The bearing effect of the rigidity piles is difficult to play due to the fact that the rigidity piles are stabbed into the grouting tubes. When the grouting tubes are grouted and after slurry is hardened, the pile caps, the slurry and the rigidity piles form a rigidity support, and the goal that the load is undertaken by the piles and soil together to reduce settlement is realized. Meanwhile, the reinforced cushion has the effects of restraining the horizontal displacement of the piles and the soil, limiting the local deformation of a dyke and a dam and the like. According to the composite foundation, the bearing force of the foundation soil can be given full play; the using amount of the rigidity piles is reduced; the stability of the foundation is improved; the post-construction settlement and differential settlement are reduced; the construction period is shortened; and the composite foundation can be applied to projects such as highways, railways and earth-rock dams.
Owner:WUYI UNIV

Elevator for deep foundation pit excavation by inverse construction method, and excavation system and method

InactiveCN101434358AAvoid smallReduce the process of digging and bargingExcavationsBuilding liftsBasementExcavator
The invention relates to the field of civil engineering construction, in particular to equipment, a system and a method used by deep foundation pit excavation construction, and discloses a lifter used by deep foundation pit excavation using a topdown construction method. The lifter comprises a bracket, a lifting mechanism and a lift car, wherein, the bracket is fixed on a basement top plate; the lifting mechanism is fixed on the bracket; the lift car is connected with the lower end of the lifting mechanism which drives the lift car to move up and down; and the lift car can load heavy construction vehicles. The invention also discloses a system and a method used by deep foundation pit excavation construction using the topdown construction method, which comprise heavy construction machinery, wherein, the heavy construction machinery comprises an earth transporting vehicle, an excavator excavating on the excavation working face of the bottom of the foundation pit as well as the lifter arranged on the basement top plate; and the heavy construction machinery realizes excavating, earth loading and earth transporting by the reciprocating transportation of the lifter between the basement top plate and the bottom of the foundation pit. The invention can effectively improve the excavation efficiency, reduce the excavation cost and reduce the influence of the underground excavation construction on the synchronous superstructure construction to the minimum.
Owner:SHANGHAI CONSTRUCTION GROUP

Deep foundation pit earthwork digging method

ActiveCN102425173AEnsure safetyAvoid repeated digging and fillingExcavationsBulkheads/pilesBuilding constructionSteel plates
The invention relates to a deep foundation pit earthwork digging method. The method comprises the following steps of: (1) after paying-off measurement of a deep foundation pit is finished, designing N layers of horizontal supporting steel plates according to the deep foundation pit engineering conditions in the deep foundation pit from top to bottom, and digging the foundation pit earthwork layerby layer by adopting an island type digging method, wherein N is more than or equal to 1 and less than or equal to 20; (2) downwards driving an outside steel plate pile along the wall of the deep foundation pit; and (3) digging the earthwork above the first layer of horizontal supporting steel plate, welding one end of the first layer of horizontal supporting steel plate to the outside steel plate pile, downwards driving an inside steel plate pile at the other end of first layer of the horizontal supporting steel plate and the like, constructing the Nth layer of horizontal supporting steel plate, building a ramp, digging the earthwork below the Nth layer of horizontal supporting steel plate, regressing, digging the ramp, removing the inside steel plate pile, digging the rest earthwork, and thus finishing digging the earthwork of the deep foundation pit. The construction method is simple and feasible; a trestle is not required, the construction period is effectively quickened, and the digging cost of the earthwork of the deep foundation pit is reduced; and the deep foundation pit earthwork digging method is safe and reliable.
Owner:MCC TIANGONG GROUP

High-slope large-scale steel penstock mounting and unloading device and steel penstock mounting method

The invention discloses a high-slope large-scale steel penstock mounting and unloading device which comprises a trolley with a rotary part, a rail and a traction device for dragging the trolley. A high-slope large-scale steel penstock mounting method comprises the following steps: (1) carrying out foundation measurement and rail laying; (2) designing and arranging the traction device; (3) manufacturing and mounting the trolley and carrying out a load test; (4) transporting steel penstocks to unloaded positions; (5) swerving the trolley and the steel penstocks; (6) unloading the steel penstocks at a first abrupt slope section; (7) swerving the trolley and the steel penstocks at a gentle slope plane; (8) unloading the steel penstocks at a second abrupt slope section; (9) putting the steel penstocks in position; and (10) disassembling and moving out the trolley. According to the high-slope large-scale steel penstock mounting and unloading device and the high-slope large-scale steel penstock mounting method, the technological problems including laying of the rail and the traction device for mounting the steel penstocks at a complicated massif terrain, design of the mounting and unloading device, horizontal transportation, right-angle swerving, unloading in a high-slope, plane swerving and in-position unloading of the steel penstocks can be solved, construction is safe and efficient, and economy and practicality are realized.
Owner:CHINA GEZHOUBA GRP MECHANICAL & ELECTRICAL CONSTR

Method for processing long-pile short-pier composite foundation

The invention relates to a method for processing a long-pile short-pier composite foundation, which sets pier-changing and inter-pier pitching piles in the foundation to satisfy the foundation bearing capacity and deformation requirements, performs pier setting mainly through a forced ramming or forced ramming displacement method, and sets sedimentation control piles between the piers. The principle of displacing pier distribution points comprises the following steps: symmetrically setting one or more displacement points for changing the piers in the length direction of an independent foundation, and setting the sedimentation control piles between the displacement points as the inter-pier pitching piles; evenly setting a plurality of displacement points for changing the piers in the length direction of a strip foundation, and arranging the sedimentation control piles between the displacement points according to the designed separation distance; and on the basis of a large size, calculating the required displacement ratio of rectangular or quincuncial distribution points for the displacing pier distribution points according to the bearing capacity, calculating the required pile number for the sedimentation control piles according to sedimentation, and arranging the piles according to rectangular or quincuncial shapes between the displacing piles. The method has the advantages of manufacturing cost saving, mature construction experience, simple process and remarkable effect, and economically and effectively solves the problems that the bearing capacity of deep made ground or a soft soil foundation is insufficient and the foundation deformation is large and uneven.
Owner:上海现代建筑设计(集团)有限公司 +2

Prefabricated internal support system and construction method for foundation pit support system

The invention discloses a prefabricated internal support system and a construction method for a foundation pit support system. The prefabricated internal support system comprises a top beam (1), an enclosing purline and an inner support (2), wherein the inner support (2) is a truss type inner support (2) assembled by splicing a pre-stressed hollow square pile (3) and a node connecting piece; first end plates on the two ends of the truss type inner support (2) are in screwed connection with a connecting plate on the top beam (1), and the rest of the first end plates are in screwed connection with second end plates of the node connecting piece; the construction method comprises the key points that the pre-stressed hollow square pile (3) and the node connecting piece are assembled into the truss type inner support (2) in a splicing manner, and the two ends of the truss type inner support (2) are connected with the top beam (1). The prefabricated internal support system and the construction method for the foundation pit support system has the advantages that the system and the method are convenient and efficient, the construction speed is high, the construction period is short, the follow-up earth cutting and earth discharging are convenient, the dismounting process is also convenient, efficient and labor-saving, no safety potential hazard is caused, the system can be recycled, and the material is saved.
Owner:宁波冶金勘察设计研究股份有限公司

Assembly type variable steel girder platform, distribution method and assembly method thereof

The invention relates to an assembly type variable steel girder platform, a distribution method and an assembly method thereof. The platform is supported on a core tube, and is formed by sectional steel grinders through being fixedly connected, and the sectional steel grinders mainly consist of main stress grinders, sub stress grinders and support rods between grinders, wherein the main stress grinders are formed by main grinder standard nodes and main grinder groined node standard nodes through being dismountably connected via node plates with bolt holes, end sealing plates with bolt holes and screw bolts, the sub stress grinders are formed by sections of sub grinder standard sections through being dismountably connected end to end, and in addition, the sub stress grinders are dismountably connected between two main stress grinders. The platform can be applied to template lifting construction of high and superhigh building core tube steel platforms, and can also be used as platforms for large-area spanning construction operation and construction machine pile carrying and placement, the construction is very easy, the work period of the construction is greatly accelerated, and the construction cost is reduced.
Owner:CHINA CONSTR THIRD ENG BUREAU GRP CO LTD +1

Lifting installation system for buckling restrained supporting member and construction method thereof

The invention provides a lifting installation system for a buckling restrained supporting member and a construction method of the lifting installation system for the buckling restrained supporting member. In the installation system, chain blocks used for lifting the buckling restrained supporting member are fixed to a beam or supporting stand columns of the buckling restrained supporting member to be installed respectively through hanging plates or temporary supports. The hanging plates and the temporary supports are simple in structure and can be used repeatedly, construction is convenient, manpower and material resources are saved, and the problems that in the current construction, the rate of progress is low, the construction can be finished only with cooperation of several persons, waste of manpower and material resources is caused, and engineering cost is high are solved. The invention further provides the normative construction method. The problems that in the prior art, construction specifications are relatively lacked, and construction methods are different and operation are not standard in current construction are solved. In addition, lifting installation performed on the buckling restrained supporting member can be finished under the condition of narrow spaces, and the problems that in the current construction, the chain blocks are applied with high requirements for spaces of construction environments, and adaptability to the narrow spaces of construction is not high are solved.
Owner:THE THIRD CONSTR ENG CO LTD OF CHINA CONSTR SECOND ENG BUREAU

Construction method of large-span double-sided arc-shaped aluminum plate curtain wall

The invention provides a construction method of a large-span double-sided arc-shaped aluminum plate curtain wall. Through the comprehensive application of a BIM technology and a lofting robot, curtainwall units are reasonably partitioned, adapting parts are reasonably arranged, and then a moulding bed, a curtain wall keel steel truss, the adapting parts and large-span double-sided arc-shaped aluminum plate curtain wall unit plates are accurately and rapidly positioned in an auxiliary mode, so that rapid on-site assembly and positioning installation are realized. According to the constructionmethod of the large-span double-sided arc-shaped aluminum plate curtain wall, the molding effect and precision of the large-span double-sided arc-shaped aluminum plate curtain wall molding are ensuredby adopting a field segmented integral molding bed preprocessing and assembling technology; through the comprehensive application of a BIM model and the lofting robot, the curtain wall keel steel truss and the adapting parts are quickly positioned and welded on site, so that the problem of positioning and mounting of a large number of adapting parts of different specifications on site is solved,the mounting accuracy is greatly improved, and the construction period is greatly shortened; and a segmented hoisting mode is adopted, and through the comprehensive application of the BIM model and the lofting robot, a curtain wall unit panel is accurately positioned, and the hoisting precision and the efficiency are improved.
Owner:CHINA CONSTR EIGHTH ENG DIV

Recursive flow process construction method for ultra-long concrete floor structure

The invention discloses a recursive flow process construction method for an ultra-long concrete floor structure. The method includes the following steps that the ultra-long concrete floor structure is partitioned; maximum tension stress and maximum shear stress of a concrete beam on a concrete floor in each bay are calculated, and the mixing proportion of concrete is adjusted; the recursive flow process construction direction of the overall concrete floor is determined; the pouring time interval between every two adjacent concrete floors is calculated; the rate of maximum hydration heat temperature raising and temperature lowering in the concrete beam and the concrete floor is determined; it is guaranteed that the maximum axial force applied to the concrete beam in the concrete hydration heat temperature raising and temperature lowering process does not exceed the bearing capacity at that time; concrete pouring is performed, and recursive flow process construction of the ultra-long concrete floor structure is completed. According to the construction method, when concrete is mixed, constraining force of the concrete beam on the concrete floor is strictly measured, if requirements are not met, the mixing proportion of the concrete is readjusted, and thus the construction quality is guaranteed.
Owner:CHINA CONSTR EIGHT ENG DIV CORP LTD

Construction equipment and method for fabricated non-dismantling formwork constructional column and ring beam

ActiveCN113846802ASave the installation and disassembly processImprove construction qualityStrutsWallsBrickArchitectural engineering
The invention relates to the technical field related to buildings, in particular to construction equipment and method for a fabricated non-dismantling formwork constructional column and a ring beam. The fabricated non-dismantling formwork constructional column comprises a plurality of U-shaped brick bodies which are different in length and connected in a staggered mode to form a formwork groove; a steel bar column is placed in the formwork groove, and a concrete pouring layer is poured between the steel bar column and the formwork groove. According to the construction equipment and method for the fabricated non-dismantling formwork constructional column and the ring beam, the design is novel, a U-shaped brick body is adopted to replace a wood formwork, a formwork mounting and dismounting procedure is omitted, the construction quality of the constructional column and the ring beam is improved, the construction efficiency is improved, the construction period is effectively shortened, the construction cost is saved, and the safety risk of edge work of the constructional column and the ring beam is greatly reduced. According to the construction equipment and method for the fabricated non-dismantling formwork constructional column and the ring beam, for the super high-rise edge constructional column, the formwork supporting and disassembling process is omitted, the construction risk is greatly reduced, a large amount of high-altitude edge operation is reduced, and the practicability is high.
Owner:CHINA RAILWAY URBAN CONSTR GRP

Truss girder, combination beam using truss girders and combination floor system using truss girders

The invention discloses a truss girder, a combination beam using truss girders and a combination floor system using truss girders. The truss girder comprises a lower chord plate, an upper chord member located above the lower chord plate and a connecting web member connecting the upper chord member with the lower chord plate. The combination beam is composed of the truss beams and concrete, and the steel and concrete combination beam is formed through construction. The combination floor system comprises main frame beams, truss beams, a plurality of light plate bottom molds and concrete floors, wherein the truss beams are supported on the main frame beams through lower chord plates, the light plate bottom molds are located between the truss beams, and the concrete floors are located on the light plate bottom molds. The whole floor system construction process does not need supporting, and the truss beams are used for bearing construction loads. The truss beams and the concrete are combined into the steel structure-concrete combined beam which is hidden in the floor system to serve as a hidden ribbed beam and bear the loads in the use stage. The combination floor system has the advantages of being low in cost, high in speed, excellent in heat preservation and noise isolation performance, light, high in strength, environmentally friendly, convenient to industrialize and the like.
Owner:杭州材智建筑科技有限公司

Construction method for steel plate concrete wall of primary loop cabin of high temperature gas cooled reactor

The invention relates to a construction method for a steel plate concrete wall of a primary loop cabin of a high temperature gas cooled reactor, which belongs to the technical field of reactor structures. The method includes: arranging inner bearing steel posts, outer bearing steel posts, bearing crossbeams and connecting beams according to design requirements, sequentially arranging shielding cooling water pipes, outer steel plates, inner steel plates and a plurality of transverse shearing nails to form a wall framework module, hoisting the module to the position of the primary loop cabin ofthe high temperature gas cooled reactor, concreting to form a lower-layer steel plate concrete wall module, hoisting an upper-layer module on the lower-layer steel plate concrete wall module, and cycling so to form the wall of the primary loop cabin of the high temperature gas cooled reactor. By the construction method, time of constructional critical paths can be shortened, cross workload on a construction site can be reduced, and work intensity on the construction site is relieved. Further, accurate execution of construction schedule can be guaranteed while construction quality is improved and construction period is shortened.
Owner:CHINERGY CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products