The invention relates to a large
tidal range marine environment steel
pipe pile lock catch
cofferdam leaking stoppage
system and a construction method. The construction method comprises the following construction steps that S1, measurement and positioning are conducted; s2, inserting and hitting a steel casing and designing a
cofferdam; s3, digging a guide hole; s4, lock catch steel
pipe piles are manufactured; s5, lock catch pretreatment; s6, hole guiding concrete is poured; s7, lock catch steel
pipe piles are inserted and driven; s8, the enclosing
purlin is put down; s9, mounting a counter-pull leakage-proof device; s10, pouring concrete in the
pile; s11, pumping water in the
cofferdam; s12, desilting is conducted in the cofferdam; s13, the enclosing
purlin lowering device is dismantled; s14, the steel casing is dismantled; s15, pouring a bearing platform; and S16, the cofferdam is dismantled. Through the design of the lock catch type steel pipe
pile, lock catches are tightly connected, and
water leakage is effectively prevented; in a high-tidal-range environment, a counter-pull leakage-proof device is adopted to push a steel strand to contract inwards through a hydraulic rod, the cofferdam is hooped, lock catch gaps are reduced, and the sealing performance of the cofferdam is further enhanced; and the design of three
layers of enclosing purlins is adopted, so that the overall stability of the cofferdam in a high-tidal-range environment is ensured.